Data center project · Charles City, Virginia
Roxbury Technology Park
Withdrawn · Diode Ventures dropped its plan to rezone about 515 acres in Charles City County after months of resident opposition, before supervisors voted.
- Status
- Withdrawn · as of Aug. 2025
- Location
- About 20 miles east of Richmond · Charles City
- Power
- Not reported
No power figure appears in the sources opened. - Land
- 515 acres
- Developer and team
- Diode Ventures
- Evidence
- News reports; primary records not yet obtained
- Size class
- 50 MW or more (tracker scope)
Updates, newest first
- Aug. 2025 Diode withdrew the rezoning request. (Richmond BizSense, Dec. 30, 2025)
- May 2025 The county planning commission recommended approval. (Richmond BizSense, Dec. 30, 2025)
Conflicts and open questions
- The map point is approximate; only the distance from Richmond was reported.
Have records about this project? Send them to tips@signaldata.org.