Data center project · Hanover, Virginia
Mountain Road Technology Park
Denied · Supervisors voted 4-3 to deny Tract's rezoning of nearly 430 acres for a data center campus, with water use the main concern.
- Status
- Denied · as of May 27, 2026
- Location
- 13074 Mountain Road and 12517 Winns Church Road, on the Henrico line · Hanover
- Power
- 900 MW
Planned capacity in the Hanover staff report, as reported; Dominion said the first phase would be energized around the end of 2029. - Land
- 430 acres
- Developer and team
- Tract
- Evidence
- News reports; primary records not yet obtained
- Size class
- 50 MW or more (tracker scope)
Updates, newest first
- May 27, 2026 Supervisors denied the rezoning 4-3 despite proffers that included $15 million for a pump station and water tank and $6 million for land conservation and parks. (Richmond BizSense, May 28, 2026)
- April 2026 The planning commission recommended approval after two deferrals. (Richmond BizSense, May 28, 2026)
- April 2026 The county staff report described a 900 MW project, and a Dominion spokesperson said its first phase would be energized toward the end of 2029. (Richmond BizSense, April 17, 2026; VPM News, April 17, 2026)
- Dec. 2025 Tract was seeking a rezoning for a master-planned data center campus in western Hanover. (Richmond BizSense, Dec. 30, 2025)
Have records about this project? Send them to tips@signaldata.org.