Data center project · Racine County, Wisconsin
Microsoft Caledonia data center (Project Nova)
Withdrawn · Microsoft dropped a three-building campus on We Energies land in Caledonia after resident opposition, days after the plan commission approved rezoning. Also known as: Project Nova.
- Status
- Withdrawn · as of Oct. 8, 2025
- Location
- Douglas Avenue and County Line Road, Village of Caledonia, across from the Oak Creek power plant · Racine County
- Power
- Not reported
No power figure published. - Land
- 244 acres
- Developer and team
- Microsoft
- Utility
- We Energies (land owner)
- Evidence
- News reports; primary records not yet obtained
- Size class
- 50 MW or more (tracker scope)
Updates, newest first
- Oct. 8, 2025 Microsoft said it would not move forward with the site, citing community feedback, a week after the plan commission approved the rezoning (two members opposed) and ahead of a scheduled Oct. 14 village board vote. (BizTimes Milwaukee, Oct. 8, 2025)
- Sept. 23, 2025 Microsoft confirmed it was the company behind Project Nova, with conceptual plans for three buildings and a substation. (BizTimes Milwaukee, Sept. 23, 2025)
- July 28, 2025 Caledonia's plan commission delayed a vote on rezoning about 240 acres of farmland for an unnamed company's data center after residents objected (WPR, July 31). (WPR, July 31, 2025)
Conflicts and open questions
- Acreage is given as 244 or 245 acres in BizTimes reports and about 240 acres by WPR.
Have records about this project? Send them to tips@signaldata.org.