Data center campus · West Columbia, Mason County, West Virginia

Project Tamarack

Approved as of Sept. 3, 2026

Starwood Capital Group's data center arm received state high impact certification for a $12 billion, grid-supplied campus of about 2.16 GW near West Columbia.

Cite← West Virginia data centers
Barbour CountyBerkeley CountyBoone CountyBraxton CountyBrooke CountyCabell CountyCalhoun CountyClay CountyDoddridge CountyFayette CountyGilmer CountyGrant CountyGreenbrier CountyHampshire CountyHancock CountyHardy CountyHarrison CountyJackson CountyJefferson CountyKanawha CountyLewis CountyLincoln CountyLogan CountyMarion CountyMarshall CountyMason CountyMcDowell CountyMercer CountyMineral CountyMingo CountyMonongalia CountyMonroe CountyMorgan CountyNicholas CountyOhio CountyPendleton CountyPleasants CountyPocahontas CountyPreston CountyPutnam CountyRaleigh CountyRandolph CountyRitchie CountyRoane CountySummers CountyTaylor CountyTucker CountyTyler CountyUpshur CountyWayne CountyWebster CountyWetzel CountyWirt CountyWood CountyWyoming CountyProject Tamarack · Approved · 2,160 MW
Power2,160MW reported · record

Who is behind it

ProjectProject Tamarack
Developer and teamStarwood Digital Ventures (through Starwood Capital Group)
End userNot found in the recordsNot yet named in any record or credited report we have found.

The record, newest first

  1. West Virginia Watch placed the site about 20 miles north of the Monarch campus and said it would take power from the grid. (West Virginia Watch (via News From The States), Sept. 8, 2026)

  2. The governor announced the project's high impact data center certification at the state Chamber of Commerce summit. (Office of the Governor of West Virginia, Sept. 3, 2026; Charleston Gazette-Mail, Sept. 3, 2026)

Conflicts and open questions

  • Jobs differ: about 1,500 (governor) vs. 1,000+ construction and 300+ permanent (project website, per Gazette-Mail).
  • No acreage, parcel or power-supply agreement is public.

The full record

Status note
Certified by the state as a high impact data center; no permits, site plan or timeline are public.
Power note
About 2.16 GW, per the governor; West Virginia Watch reported the power would come from the existing grid.
Evidence
Primary public records
Size class
50 MW or more (tracker scope)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.