Data center campus · Venture Drive, Campstool Business Park area, northeast Cheyenne, Laramie County, Wyoming

CleanSpark Cheyenne (Campstool Business Park / Venture Drive)

Operating as of Aug. 4, 2026

CleanSpark's first Wyoming bitcoin mining site, an immersion-cooled facility in a light-industrial park in northeast Cheyenne, which drew a noise complaint from nearby residents in 2025. Also known as: CleanSpark - East.

Cite← Wyoming data centers
Albany CountyBig Horn CountyCampbell CountyCarbon CountyConverse CountyCrook CountyFremont CountyGoshen CountyHot Springs CountyJohnson CountyLaramie CountyLincoln CountyNatrona CountyNiobrara CountyPark CountyPlatte CountySheridan CountySublette CountySweetwater CountyTeton CountyUinta CountyWashakie CountyWeston CountyCleanSpark Cheyenne (Campstool Business Park / Venture Drive) · Operating · 42 MW
Power42MW reported · stated

Who is behind it

ProjectCleanSpark Cheyenne (Campstool Business Park / Venture Drive)Also: CleanSpark - East
Developer and teamCleanSpark (through CleanSpark, Inc.)
End userNot found in the recordsNot yet named in any record or credited report we have found.

The record, newest first

  1. Cheyenne LEADS listed 'CleanSpark - East' as a current data center. (Cheyenne LEADS, Aug. 4, 2026)

  2. Residents of a nearby rural subdivision described a constant low rumble; CleanSpark said sound mitigation was still being put in place, and the mayor said the city was testing that noise stays within the property line, as light-industrial zoning requires. (Cowboy State Daily, March 16, 2025)

  3. CleanSpark said it had completed the purchase of its first Wyoming site, 30 MW in Cheyenne, with groundbreaking to start right away. (CleanSpark, Inc. (SEC Form 8-K, Exhibit 99.1), Aug. 1, 2024; Wyoming Tribune Eagle, Sept. 20, 2024)

Conflicts and open questions

  • The Tribune Eagle placed the first site in Campstool Business Park; Cowboy State Daily placed CleanSpark's running site on Venture Drive in the northeast industrial park. They are treated as the same site; matching it to LEADS's 'CleanSpark - East' is an inference.
  • Under 50 MW; kept because it is operating.
  • Coordinates approximate.

The full record

Status note
In March 2025 seven immersion-cooled units were running, with four more planned, while the site was still being finished; Cheyenne LEADS listed 'CleanSpark - East' as current in August 2026.
Power note
42 MW running in March 2025 (seven 6 MW units), with 11 units planned; CleanSpark's 2024 release gave the first site 30 MW.