Data center campus · Cheyenne Business Parkway, east Cheyenne, north of I-80, Laramie County, Wyoming

Microsoft Cheyenne Business Parkway campus

Operating as of Aug. 4, 2026

A Microsoft data center site in the roughly 900-acre Cheyenne Business Parkway on the east side of Cheyenne, announced in 2021 and operating by 2024, with more Microsoft buildings listed as under construction or planned.

Cite← Wyoming data centers
Albany CountyBig Horn CountyCampbell CountyCarbon CountyConverse CountyCrook CountyFremont CountyGoshen CountyHot Springs CountyJohnson CountyLaramie CountyLincoln CountyNatrona CountyNiobrara CountyPark CountyPlatte CountySheridan CountySublette CountySweetwater CountyTeton CountyUinta CountyWashakie CountyWeston CountyMicrosoft Cheyenne Business Parkway campus · Operating
PowerNot statedNot reported in the records found

Who is behind it

ProjectMicrosoft Cheyenne Business Parkway campus
Developer and teamMicrosoft
End userMicrosoft (Azure West Central US region)

The record, newest first

  1. Cheyenne LEADS listed 'Microsoft - CBP' among current data centers, again among those under construction, and again among planned sites. (Cheyenne LEADS, Aug. 4, 2026)

  2. The Tribune Eagle reported one Microsoft data center in the park and a second slated to be built. (Wyoming Tribune Eagle, April 3, 2024)

  3. Microsoft announced two new Cheyenne datacenters, one in Cheyenne Business Parkway and one in Bison Business Park, to expand its West Central US cloud region. (Cheyenne LEADS, Nov. 22, 2021; Cowboy State Daily (via Data Center Dynamics), Nov. 23, 2021)

Conflicts and open questions

  • Coordinates approximate, placed at the reported location of Cheyenne Business Parkway (east of central Cheyenne, north of I-80).
  • The 385-acre site east of College Drive that Microsoft applied for in May 2026 is tracked with the southeast expansion, because Microsoft told Cowboy State Daily it is near the 3,200-acre tract and LEADS said it adjoins Bison Business Park.
  • Size and MW not reported. LEADS lists several Microsoft CBP entries without separating buildings; which are new buildings at this campus was not confirmed.
  • Utility arrangement is from Microsoft's April 14, 2026 release (wy-msft-source-20260414).

The full record

Status note
Microsoft announced a new datacenter in the park in November 2021; the Tribune Eagle reported one Microsoft data center there in April 2024 with a second slated, and Cheyenne LEADS in August 2026 listed Microsoft CBP sites as current, under construction and planned.
Evidence
Primary public records
Size class
Under 50 MW (outside main scope; kept for completeness)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.