Data center campus · HR Ranch Road, east/southeast Cheyenne, in the area of the Cheyenne Prairie Generating Station and Dry Creek wastewater plant, Laramie County, Wyoming

Microsoft HR Ranch Road datacenter

Under construction as of Sept. 25, 2026

A Microsoft datacenter under construction on HR Ranch Road on the east side of Cheyenne, begun in mid-2025.

Cite← Wyoming data centers
Albany CountyBig Horn CountyCampbell CountyCarbon CountyConverse CountyCrook CountyFremont CountyGoshen CountyHot Springs CountyJohnson CountyLaramie CountyLincoln CountyNatrona CountyNiobrara CountyPark CountyPlatte CountySheridan CountySublette CountySweetwater CountyTeton CountyUinta CountyWashakie CountyWeston CountyMicrosoft HR Ranch Road datacenter · Under construction
PowerNot statedNot reported in the records found

Who is behind it

ProjectMicrosoft HR Ranch Road datacenter
Developer and teamMicrosoft
End userMicrosoft

The record, newest first

  1. Cowboy State Daily described construction as well under way at the Microsoft hyperscale data center on HR Ranch Road in east Cheyenne. (Cowboy State Daily, Sept. 25, 2026)

  2. DCD reported the groundbreaking and noted HR Ranch Road is home to the Cheyenne Prairie Generating Station and the Dry Creek wastewater plant; Microsoft gave no size or cost. (Data Center Dynamics, Aug. 15, 2025)

  3. Microsoft posted that it was building a datacenter on HR Ranch Road, with heavy earthwork from July to November 2025, JE Dunn as general contractor, completion targeted for early 2026 and a community meeting planned for November. (Microsoft Local, Aug. 14, 2025)

Conflicts and open questions

  • Coordinates are a rough placement in east Cheyenne based on DCD's description of nearby facilities; no address or parcel was found. Low confidence.
  • Size, MW and investment not disclosed. Treated as a separate campus from Cheyenne Business Parkway and Bison because sources describe it as its own site; it may correspond to one of the unnamed Microsoft entries on the LEADS August 2026 list. Confirm with a county or city site plan.
  • Microsoft cautioned that finished construction does not mean the building is operating.
  • Utility arrangement is from Microsoft's April 14, 2026 release (wy-msft-source-20260414).

The full record

Status note
Microsoft began construction in mid-2025 with JE Dunn as general contractor, expecting 18 to 24 months of work; Cowboy State Daily described construction as well under way in September 2026. Operation was not confirmed in an opened source.
Evidence
Primary public records
Size class
Under 50 MW (outside main scope; kept for completeness)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.