Data centers · New Haven County, Connecticut

New Haven County

2 projects on record · 2 moratorium or ban actions

← Statewide map
Fairfield CountyHartford CountyLitchfield CountyMiddlesex CountyNew Haven CountyNew London CountyTolland CountyWindham CountyBeacon Falls Data Center (O&G Industries) · Site zoned or marketed · 100 MWTierPoint Waterbury · Operating
Projects in New Haven County
Beacon Falls Data Center (O&G Industries)O&G Industries100Site zoned or marketedOct. 25, 202650 MW+
TierPoint WaterburyTierPoint—OperatingOct. 2026Under 50 MW

Moratoriums and bans

  1. June 8, 2026 West Haven: Moratorium. The City Council unanimously approved a 12-month suspension of permit processing and zoning actions for new data centers, so planning staff can study impacts and draft regulations. Connecticut Public confirms the one-year moratorium; the date and vote come from a meeting-video aggregator. (CitizenPortal.ai (aggregator of meeting video; minor detail only), June 8, 2026; Connecticut Public, Sept. 11, 2026)
  2. Sept. 2026 New Haven: Moratorium. Alder Richard Furlow proposed a 12-month pause on accepting or approving applications for new data centers or conversions while a city working group drafts zoning standards. The Legislation Committee forwarded it favorably on Aug 4, 2026, and the Board of Alders adopted it in September 2026 with an exemption for the city's quantum computing hub. (Hartford Business Journal, July 2026; CitizenPortal.ai (aggregator of meeting video; minor detail only), Aug. 4, 2026; CT Mirror, Oct. 25, 2026)

Updates, newest first

  1. Oct. 26, 2026 TierPoint Waterbury · TierPoint's website lists Waterbury as its only Connecticut data center, with more than 3,000 sq ft and two on-site backup generators of 125 kW and 400 kW. (TierPoint, Oct. 26, 2026)
  2. Sept. 2026 New Haven: Moratorium · Alder Richard Furlow proposed a 12-month pause on accepting or approving applications for new data centers or conversions while a city working group drafts zoning standards. The Legislation Committee forwarded it favorably on Aug 4, 2026, and the Board of Alders adopted it in September 2026 with an exemption for the city's quantum computing hub. (Hartford Business Journal, July 2026; CitizenPortal.ai (aggregator of meeting video; minor detail only), Aug. 4, 2026; CT Mirror, Oct. 25, 2026)
  3. Aug. 2026 Beacon Falls Data Center (O&G Industries) · About a dozen residents urged the Planning and Zoning Commission to adopt a data center moratorium. The first selectman said O&G had asked over the summer whether the town would consider a second agreement for a revised plan, but no specifics followed. (CT Mirror, Oct. 25, 2026)
  4. June 8, 2026 West Haven: Moratorium · The City Council unanimously approved a 12-month suspension of permit processing and zoning actions for new data centers, so planning staff can study impacts and draft regulations. Connecticut Public confirms the one-year moratorium; the date and vote come from a meeting-video aggregator. (CitizenPortal.ai (aggregator of meeting video; minor detail only), June 8, 2026; Connecticut Public, Sept. 11, 2026)
  5. 2023 Beacon Falls Data Center (O&G Industries) · The 2022 agreement lapsed before a host fee agreement was finalized, as the developers did not find a buyer. (CT Mirror, Oct. 25, 2026)
  6. April 21, 2022 Beacon Falls Data Center (O&G Industries) · A special town meeting unanimously approved an agreement between Beacon Falls and O&G's CT Data Center for a two-story, 32 MW, about 294,000 sq ft facility. The selectmen had approved it on April 11. (DatacenterDynamics (crediting My Citizen News), April 2022)

Statewide

Public Act 21-1 (HB 6514, 2021 regular session; approved Mar 4, 2021, effective Jul 1, 2021; codified at CGS 32-286) lets DECD sign 20-year agreements with 'qualified data centers' that invest at least $50M in an enterprise zone or federal opportunity zone, or $200M elsewhere, within five years; terms stretch to 30 years at $200M in a zone or $400M elsewhere. (Connecticut General Assembly, March 4, 2021; Connecticut General Assembly, Office of Legislative Research, Dec. 20, 2024) Under PA 21-1, a qualifying project is exempt from sales and use tax on data center equipment, related services and the electricity it uses, and from local property tax on its real property and IT equipment; projects at the 30-year level also get a 30-year exemption from any future state financial transactions tax. DECD can charge an annual fee of up to $50,000 during the qualifying period. (Connecticut General Assembly, March 4, 2021; Connecticut General Assembly, Office of Legislative Research, Feb. 24, 2021; Connecticut DECD, undated) PA 21-1 requires the owner to sign a negotiated fee agreement with each host municipality before construction starts. The agreement covers how the exempted property tax is paid and the penalties for noncompliance. If a breach is not cured within 180 days, the agreement ends and the property becomes taxable. (Connecticut General Assembly, March 4, 2021; Connecticut General Assembly, Office of Legislative Research, Feb. 24, 2021) The Senate passed the 2021 incentive bill 29-5 on Mar 1, 2021. As of Oct 2026, DECD has reviewed only two applications under the program, and CT Mirror reports that the only project to use the sales tax exemption is Cigna's $386M renovation of an existing data center in Windsor. (CT Mirror, March 1, 2021; CT Mirror, Oct. 25, 2026) SB 1353 (2025), 'An Act Concerning Subsidies for New Electricity Demand', would have rewritten the definitions in CGS 32-286. Among other changes, it would have left out facilities powered by a customer-side (behind-the-meter) supplier unless that supplier adds enough new generation to offset all of the facility's electric use. Energy and Technology reported a substitute bill and sent it to Finance; its final outcome was not confirmed from a CGA status page. (Connecticut General Assembly, 2025) SB 299 (2024 session) would have had PURA begin a proceeding by Jul 1, 2024, working with OCC, DEEP and ISO New England, on how large data centers could affect grid reliability; the committee co-chair said it was written with the behind-the-meter NE Edge plan at Millstone in mind. Energy and Technology approved it Mar 21, 2024; no resulting Public Act was found. (American Public Power Association, March 25, 2024; CT Mirror, March 7, 2024) SB 245 (2026), 'An Act Eliminating Certain Tax Incentives for Data Centers', got a joint favorable report from Energy and Technology on Mar 17, 2026. It was referred to Finance, Revenue and Bonding on Mar 23, 2026 and saw no further action, so it was not enacted. (Connecticut General Assembly, March 17, 2026; Connecticut General Assembly, March 23, 2026) HB 5469 (2026), 'An Act Concerning Colocated Electric Suppliers and Large Electric Load Customers', aimed at loads of 50 MW or more. It would have required PURA licensing of co-located (behind-the-meter) suppliers covering 100% of load from new generation in service on or after Jul 1, 2026. Eversource, UI and municipal utilities would have had to file large-load tariffs by Apr 1, 2027, with 85%/10-year payment guarantees and deposits, and PURA would have had to open a proceeding by Jan 1, 2027. Energy and Technology approved it 26-0 on Mar 19, 2026, and it reached the House as File 421. No Public Act was found. (Connecticut General Assembly, Office of Legislative Research, April 7, 2026; Hartford Business Journal, March 2026) PURA: no Connecticut docket specific to data centers or large-load tariffs was found in the records reviewed. The OLR's Dec 2024 report on electricity demand cites no such docket, and the PURA proceeding in HB 5469 would have been required only if that bill became law. (Connecticut General Assembly, Office of Legislative Research, Dec. 20, 2024; Connecticut General Assembly, Office of Legislative Research, April 7, 2026) Siting: the Connecticut Siting Council has exclusive jurisdiction over the site of a power-generating facility, but reporting describes it as having no authority over a data center on its own. One example is Petition 1533A (ReNew Developers, with Bloom Energy), an 18 MW fuel cell addition at 42 Old Amston Road, Colchester, meant to supply about 99% of the base load of a second data center at the Connecticut Data Park; the Council reopened the matter Jul 20, 2023 and set Jan 16, 2024 as its decision deadline. HB 5469 (2026) said it would not limit the Council's siting authority. (Connecticut Siting Council, Nov. 3, 2023; WFSB, July 15, 2026; Connecticut General Assembly, Office of Legislative Research, April 7, 2026) Senate Majority Leader Bob Duff (D-Norwalk) has announced plans to file legislation for a statewide moratorium on new AI data centers when the 2027 session opens. No bill number exists yet. (Connecticut Public (via NHPR), Oct. 26, 2026; CT Mirror, Oct. 25, 2026) Connecticut data centers →