Data center campus · West Strickland Street near Bright Star Road, Douglasville, Douglas County, Georgia
Amazon West Strickland Street campus
Approved
as of Sept. 2025
A four-building Amazon data center campus planned on 132 industrial acres near downtown Douglasville, where the city approved taller water towers in 2025.
PowerNot statedNot reported in the records found
Site132acres
Who is behind it
ProjectAmazon West Strickland Street campus
Developer and teamAmazon Data Services
End userAWS
The record, newest first
Douglasville approved a height variance for five 50-foot water cooling towers at the 132-acre site; Amazon Data Services withdrew requests to shrink stream and impervious-surface setbacks. (Douglas County Sentinel, Sept. 3, 2025)
AWS announced at least $5 billion for data center campuses in Douglas County. (Douglas County Georgia News (Substack), Jan. 8, 2025)
Conflicts and open questions
- The variance vote date was not given; status reflects the variance approval and existing industrial zoning, not a building permit.
- MW not reported. The $5 billion Douglas pledge also covers the Echo Road site (aws-douglas-county).
- The Sentinel article gives five towers in the variance and six in the plans.
The full record
- Evidence
- News reports; primary records not yet obtained
- Size class
- 50 MW or more (tracker scope)