Data center campus · Athena Drive, northeast Athens (east of the Loop), Clarke County, Georgia

Athena Studios data center conversion

Proposed as of Dec. 10, 2025

The owner of Athena Studios proposed turning the Athens film studio and surrounding land into a roughly 1.3 million sq ft data center that county staff say needs industrial rezoning.

Cite← Georgia data centers
Appling CountyAtkinson CountyBacon CountyBaker CountyBaldwin CountyBanks CountyBarrow CountyBartow CountyBen Hill CountyBerrien CountyBibb CountyBleckley CountyBrantley CountyBrooks CountyBryan CountyBulloch CountyBurke CountyButts CountyCalhoun CountyCamden CountyCandler CountyCarroll CountyCatoosa CountyCharlton CountyChatham CountyChattahoochee CountyChattooga CountyCherokee CountyClarke CountyClay CountyClayton CountyClinch CountyCobb CountyCoffee CountyColquitt CountyColumbia CountyCook CountyCoweta CountyCrawford CountyCrisp CountyDade CountyDawson CountyDecatur CountyDeKalb CountyDodge CountyDooly CountyDougherty CountyDouglas CountyEarly CountyEchols CountyEffingham CountyElbert CountyEmanuel CountyEvans CountyFannin CountyFayette CountyFloyd CountyForsyth CountyFranklin CountyFulton CountyGilmer CountyGlascock CountyGlynn CountyGordon CountyGrady CountyGreene CountyGwinnett CountyHabersham CountyHall CountyHancock CountyHaralson CountyHarris CountyHart CountyHeard CountyHenry CountyHouston CountyIrwin CountyJackson CountyJasper CountyJeff Davis CountyJefferson CountyJenkins CountyJohnson CountyJones CountyLamar CountyLanier CountyLaurens CountyLee CountyLiberty CountyLincoln CountyLong CountyLowndes CountyLumpkin CountyMacon CountyMadison CountyMarion CountyMcDuffie CountyMcIntosh CountyMeriwether CountyMiller CountyMitchell CountyMonroe CountyMontgomery CountyMorgan CountyMurray CountyMuscogee CountyNewton CountyOconee CountyOglethorpe CountyPaulding CountyPeach CountyPickens CountyPierce CountyPike CountyPolk CountyPulaski CountyPutnam CountyQuitman CountyRabun CountyRandolph CountyRichmond CountyRockdale CountySchley CountyScreven CountySeminole CountySpalding CountyStephens CountyStewart CountySumter CountyTalbot CountyTaliaferro CountyTattnall CountyTaylor CountyTelfair CountyTerrell CountyThomas CountyTift CountyToombs CountyTowns CountyTreutlen CountyTroup CountyTurner CountyTwiggs CountyUnion CountyUpson CountyWalker CountyWalton CountyWare CountyWarren CountyWashington CountyWayne CountyWebster CountyWheeler CountyWhite CountyWhitfield CountyWilcox CountyWilkes CountyWilkinson CountyWorth CountyAthena Studios data center conversion · Proposed
PowerNot statedNot reported in the records found
Floor area1,300,000sq ft

Who is behind it

ProjectAthena Studios data center conversion
Developer and teamReynolds Capital
W&A Engineering
End userNot found in the recordsNot yet named in any record or credited report we have found.

The record, newest first

  1. The commission extended the moratorium to June 5, 2026. (The Red & Black, March 4, 2026)

  2. The studio said it would keep filming while preparing to move toward a data center if necessary. (WSB-TV, Dec. 17, 2025)

  3. The AJC reported the proposal would convert soundstages and add new buildings, about 1.3 million sq ft in all. (The Atlanta Journal-Constitution, Dec. 15, 2025)

  4. Plans were reviewed by county planners; the same night, Athens-Clarke commissioners unanimously passed a data center moratorium and the manager said the site would need industrial zoning. (WUGA, Dec. 3, 2025; Flagpole, Dec. 10, 2025)

Conflicts and open questions

  • Neither power nor acreage has been published, so the 50 MW / 100 acre scope test cannot be confirmed; kept because of the 1.3 million sq ft size. Editor may drop.
  • WSB-TV gave 185,000 sq ft (the existing studio space); AJC and Flagpole give about 1.3 million sq ft for the full plan.
  • No 2026 filing or rezoning application for the site was found.
  • What happened after the moratorium expired on June 5, 2026 was not checked (search limit reached during verification).

The full record

Status note
Plans were reviewed Dec. 2, 2025, but the county manager said the E-I zoning does not allow a data center; Athens then adopted a moratorium.
Evidence
News reports; primary records not yet obtained
Size class
Under 50 MW (outside main scope; kept for completeness)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.