Athena Studios data center conversion
The owner of Athena Studios proposed turning the Athens film studio and surrounding land into a roughly 1.3 million sq ft data center that county staff say needs industrial rezoning.
Who is behind it
W&A Engineering
The record, newest first
The commission extended the moratorium to June 5, 2026. (The Red & Black, March 4, 2026)
The studio said it would keep filming while preparing to move toward a data center if necessary. (WSB-TV, Dec. 17, 2025)
The AJC reported the proposal would convert soundstages and add new buildings, about 1.3 million sq ft in all. (The Atlanta Journal-Constitution, Dec. 15, 2025)
Plans were reviewed by county planners; the same night, Athens-Clarke commissioners unanimously passed a data center moratorium and the manager said the site would need industrial zoning. (WUGA, Dec. 3, 2025; Flagpole, Dec. 10, 2025)
Conflicts and open questions
- Neither power nor acreage has been published, so the 50 MW / 100 acre scope test cannot be confirmed; kept because of the 1.3 million sq ft size. Editor may drop.
- WSB-TV gave 185,000 sq ft (the existing studio space); AJC and Flagpole give about 1.3 million sq ft for the full plan.
- No 2026 filing or rezoning application for the site was found.
- What happened after the moratorium expired on June 5, 2026 was not checked (search limit reached during verification).
The full record
- Status note
- Plans were reviewed Dec. 2, 2025, but the county manager said the E-I zoning does not allow a data center; Athens then adopted a moratorium.
- Evidence
- News reports; primary records not yet obtained
- Size class
- Under 50 MW (outside main scope; kept for completeness)