Data center campus · 218 Industrial Park Road, north Cartersville near U.S. 411 and I-75, Bartow County, Georgia
DataBank Cartersville campus
Approved
as of Sept. 3, 2026
A DataBank campus of two 664,000 sq ft buildings, a switching station and a substation on a 69-acre former CETCO industrial site that Cartersville rezoned to technology use in September 2026. Also known as: Project Indo.
Power200MW reported · stated
Floor area1,353,000sq ft
Site69acres
Who is behind it
ProjectDataBank Cartersville campusAlso: Project Indo
Developer and teamDataBank
End userNot found in the recordsNot yet named in any record or credited report we have found.
The record, newest first
Cartersville City Council unanimously rezoned the site from heavy industrial to technology and cut required parking, on condition it be used only as a data center and get no occupancy permit until power is secured. (The Daily Tribune News (Cartersville), Sept. 7, 2026)
A regional-impact review (DRI 4761, Project Indo) was filed; reporting said DataBank planned a 200 MW, roughly 1.1 million sq ft campus with a first phase around 2032. (Georgia Department of Community Affairs, Oct. 30, 2026; iRecruit, June 23, 2026)
Conflicts and open questions
- Floor area: about 1.1 million sq ft in the DRI as reported; the council-approved site plan shows two 664,000 sq ft buildings plus a 25,000 sq ft building (about 1.35 million sq ft). The latter is shown.
- A speaker at the hearing noted that a tributary of the Etowah River runs along the property.
- Distinct from the Etowah River proposal (111 acres), tracked as etowah-river-cartersville.
The full record
- Power note
- 200 MW campus per the DRI filing as reported; a 288 MW grid connection was also requested.
- Evidence
- Primary public records
- Size class
- 50 MW or more (tracker scope)