Data center campus · 200 Selig Drive (ATL4) and a nearby 95-acre site, Lithia Springs area, Fulton County, Georgia

DataBank Lithia Springs campus (ATL4, ATL5)

Under construction as of Oct. 30, 2026

DataBank's two-site Lithia Springs campus: a fully leased 40 MW ATL4 on 18 acres and a 95-acre, up to 120 MW ATL5 site half a mile away. Also known as: ATL4, ATL5, ATL6.

Cite← Georgia data centers
Appling CountyAtkinson CountyBacon CountyBaker CountyBaldwin CountyBanks CountyBarrow CountyBartow CountyBen Hill CountyBerrien CountyBibb CountyBleckley CountyBrantley CountyBrooks CountyBryan CountyBulloch CountyBurke CountyButts CountyCalhoun CountyCamden CountyCandler CountyCarroll CountyCatoosa CountyCharlton CountyChatham CountyChattahoochee CountyChattooga CountyCherokee CountyClarke CountyClay CountyClayton CountyClinch CountyCobb CountyCoffee CountyColquitt CountyColumbia CountyCook CountyCoweta CountyCrawford CountyCrisp CountyDade CountyDawson CountyDecatur CountyDeKalb CountyDodge CountyDooly CountyDougherty CountyDouglas CountyEarly CountyEchols CountyEffingham CountyElbert CountyEmanuel CountyEvans CountyFannin CountyFayette CountyFloyd CountyForsyth CountyFranklin CountyFulton CountyGilmer CountyGlascock CountyGlynn CountyGordon CountyGrady CountyGreene CountyGwinnett CountyHabersham CountyHall CountyHancock CountyHaralson CountyHarris CountyHart CountyHeard CountyHenry CountyHouston CountyIrwin CountyJackson CountyJasper CountyJeff Davis CountyJefferson CountyJenkins CountyJohnson CountyJones CountyLamar CountyLanier CountyLaurens CountyLee CountyLiberty CountyLincoln CountyLong CountyLowndes CountyLumpkin CountyMacon CountyMadison CountyMarion CountyMcDuffie CountyMcIntosh CountyMeriwether CountyMiller CountyMitchell CountyMonroe CountyMontgomery CountyMorgan CountyMurray CountyMuscogee CountyNewton CountyOconee CountyOglethorpe CountyPaulding CountyPeach CountyPickens CountyPierce CountyPike CountyPolk CountyPulaski CountyPutnam CountyQuitman CountyRabun CountyRandolph CountyRichmond CountyRockdale CountySchley CountyScreven CountySeminole CountySpalding CountyStephens CountyStewart CountySumter CountyTalbot CountyTaliaferro CountyTattnall CountyTaylor CountyTelfair CountyTerrell CountyThomas CountyTift CountyToombs CountyTowns CountyTreutlen CountyTroup CountyTurner CountyTwiggs CountyUnion CountyUpson CountyWalker CountyWalton CountyWare CountyWarren CountyWashington CountyWayne CountyWebster CountyWheeler CountyWhite CountyWhitfield CountyWilcox CountyWilkes CountyWilkinson CountyWorth CountyDataBank Lithia Springs campus (ATL4, ATL5) · Under construction · 160 MW
Power160MW reported · stated
Floor area1,200,000sq ft
Site113acres
IT load160MW

Who is behind it

ProjectDataBank Lithia Springs campus (ATL4, ATL5)Also: ATL4, ATL5, ATL6
Developer and teamDataBank
End userNot found in the recordsNot yet named in any record or credited report we have found.

The record, newest first

  1. A data center directory lists ATL4 at 200 Selig Drive SW as operational (built 2024) and ATL5 at 4764 Bakers Ferry Road SW in the City of South Fulton as under construction, planned for 2026. (Baxtel, Oct. 30, 2026; Baxtel, Oct. 30, 2026)

  2. DataBank said ATL4, single-tenant and fully leased, was under construction for a third-quarter 2024 opening. (DataBank (PR Newswire), Nov. 28, 2023)

  3. DataBank bought about 95 acres within half a mile for two multi-story buildings of up to 1 million sq ft and 120 MW. (DataBank (PR Newswire), Oct. 31, 2023; The Atlanta Journal-Constitution, Nov. 1, 2023; CommercialSearch, Nov. 6, 2023)

  4. DataBank bought 18 acres at 200 Selig Drive for ATL4, planned at 40 MW of IT load. (DataBank (PR Newswire), May 17, 2022)

Conflicts and open questions

  • County: the AJC places ATL4 in Fulton near the Douglas line and captions ATL5 as in Douglas County, but a directory lists ATL5 at 4764 Bakers Ferry Road SW in the City of South Fulton (Fulton County). Editor: consider splitting into two records.
  • ATL4 opening (Q3 2024 target) is supported only by a directory listing it as operational and built in 2024; DataBank's location page was not opened.
  • acres = 18 + 95; sqft = 200,000 (ATL4) + about 1 million (ATL5).

The full record

Status note
ATL5 is listed as under construction (planned 2026) and ATL4 as operating, per a data center directory; no newer primary record was found.
Power note
ATL4 is planned for 40 MW of critical IT load and the 95-acre ATL5 site for up to 120 MW of critical IT (DataBank); the AJC reported 180 MW for ATL5, which matches the substation size.
Evidence
News reports; primary records not yet obtained
Size class
50 MW or more (tracker scope)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.