Data center campus · Hampton, Henry County, Georgia

Equinix Hampton campus (xScale)

Under construction as of March 6, 2026

A four-building Equinix campus on about 262 acres in Hampton, placed in its xScale hyperscale venture and served under a 20-year Central Georgia EMC power contract. Also known as: Equinix xScale Hampton.

Cite← Georgia data centers
Appling CountyAtkinson CountyBacon CountyBaker CountyBaldwin CountyBanks CountyBarrow CountyBartow CountyBen Hill CountyBerrien CountyBibb CountyBleckley CountyBrantley CountyBrooks CountyBryan CountyBulloch CountyBurke CountyButts CountyCalhoun CountyCamden CountyCandler CountyCarroll CountyCatoosa CountyCharlton CountyChatham CountyChattahoochee CountyChattooga CountyCherokee CountyClarke CountyClay CountyClayton CountyClinch CountyCobb CountyCoffee CountyColquitt CountyColumbia CountyCook CountyCoweta CountyCrawford CountyCrisp CountyDade CountyDawson CountyDecatur CountyDeKalb CountyDodge CountyDooly CountyDougherty CountyDouglas CountyEarly CountyEchols CountyEffingham CountyElbert CountyEmanuel CountyEvans CountyFannin CountyFayette CountyFloyd CountyForsyth CountyFranklin CountyFulton CountyGilmer CountyGlascock CountyGlynn CountyGordon CountyGrady CountyGreene CountyGwinnett CountyHabersham CountyHall CountyHancock CountyHaralson CountyHarris CountyHart CountyHeard CountyHenry CountyHouston CountyIrwin CountyJackson CountyJasper CountyJeff Davis CountyJefferson CountyJenkins CountyJohnson CountyJones CountyLamar CountyLanier CountyLaurens CountyLee CountyLiberty CountyLincoln CountyLong CountyLowndes CountyLumpkin CountyMacon CountyMadison CountyMarion CountyMcDuffie CountyMcIntosh CountyMeriwether CountyMiller CountyMitchell CountyMonroe CountyMontgomery CountyMorgan CountyMurray CountyMuscogee CountyNewton CountyOconee CountyOglethorpe CountyPaulding CountyPeach CountyPickens CountyPierce CountyPike CountyPolk CountyPulaski CountyPutnam CountyQuitman CountyRabun CountyRandolph CountyRichmond CountyRockdale CountySchley CountyScreven CountySeminole CountySpalding CountyStephens CountyStewart CountySumter CountyTalbot CountyTaliaferro CountyTattnall CountyTaylor CountyTelfair CountyTerrell CountyThomas CountyTift CountyToombs CountyTowns CountyTreutlen CountyTroup CountyTurner CountyTwiggs CountyUnion CountyUpson CountyWalker CountyWalton CountyWare CountyWarren CountyWashington CountyWayne CountyWebster CountyWheeler CountyWhite CountyWhitfield CountyWilcox CountyWilkes CountyWilkinson CountyWorth CountyEquinix Hampton campus (xScale) · Under construction · 240 MW
Power240MW reported · stated
Site262acres

Who is behind it

ProjectEquinix Hampton campus (xScale)Also: Equinix xScale Hampton
Developer and teamEquinix
Equinix xScale joint venture
End userNot found in the recordsNot yet named in any record or credited report we have found.

The record, newest first

  1. Equinix announced a 20-year take-or-pay contract with Central Georgia EMC covering grid upgrades, a new substation and two transmission lines for the site. (Equinix (press release), Aug. 6, 2026)

  2. County property records showed Equinix paid over $118 million for 262 acres zoned industrial; a four-building campus was planned and construction was affecting neighbors. (The Atlanta Journal-Constitution, March 6, 2026)

  3. Equinix contributed the Hampton asset to its xScale joint venture so the venture could lease it to a customer (month only). (Equinix Inc. (SEC Form 8-K exhibit), Feb. 11, 2026)

  4. At its analyst day, Equinix presented Hampton as a 240 MW xScale and retail campus. (ServeTheHome, Sept. 25, 2025)

  5. Equinix said its Hampton site of several hundred acres was being graded for construction and that it was working with a local power company. (RCR Wireless News, Aug. 13, 2025)

Conflicts and open questions

  • Equinix says the site could generate up to $20 million a year in property taxes.
  • Distinct from Hampton Technology Park and the Henderson Farms data center, also in Hampton.
  • Tenant not disclosed.

The full record

Status note
Site work and construction were under way by 2025-2026; Equinix moved the asset into its xScale joint venture in January 2026 for a customer lease.
Power note
240 MW as presented at Equinix's 2025 analyst day, per ServeTheHome.
Evidence
Primary public records
Size class
50 MW or more (tracker scope)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.