Data center campus · Hampton (requires annexation), Henry County, Georgia
Hampton Technology Park
Proposed
as of March 6, 2026
A proposed five-building, 4 million sq ft, 1,500 MW data center campus on about 604 acres that needs annexation and rezoning by Hampton and prompted the city's moratoriums. Also known as: DRI 4624.
Power1,500MW reported · record
Floor area4,000,000sq ft
Site603.56acres
Who is behind it
ProjectHampton Technology ParkAlso: DRI 4624
Developer and teamHampton Technology Park Owner LLC
End userNot found in the recordsNot yet named in any record or credited report we have found.
The record, newest first
The AJC reported the 604-acre proposal must be annexed and rezoned and had prompted Hampton moratoriums on annexations and data center requests. (The Atlanta Journal-Constitution, March 6, 2026)
Hampton submitted DRI 4624 for five buildings totaling 4 million sq ft on about 603.56 acres, listing a 1,500 MW peak load from Georgia Power and completion by 2033. (Georgia Department of Community Affairs, Feb. 13, 2026; Georgia Department of Community Affairs, Feb. 13, 2026; Georgia Department of Community Affairs, Oct. 30, 2026)
Conflicts and open questions
- DRI 4624 lists it as a continuation of an earlier DRI, Lower Woolsey Henry 780 (DRI 2808).
- The AJC reports 604 acres; the DRI gives about 603.56 acres.
The full record
- Status note
- Needs annexation and rezoning by Hampton; the city paused new annexations and data center requests in February 2026.
- Power note
- Estimated peak connected load in DRI 4624.
- Evidence
- Primary public records
- Size class
- 50 MW or more (tracker scope)