A two-building, roughly 347,000 sq ft campus with a substation on 31 acres along I-75 that Marietta rezoned unanimously in June 2025 and that drew renewed protest in 2026. Also known as: Grindcap Marietta campus.

Cite← Georgia data centers
Appling CountyAtkinson CountyBacon CountyBaker CountyBaldwin CountyBanks CountyBarrow CountyBartow CountyBen Hill CountyBerrien CountyBibb CountyBleckley CountyBrantley CountyBrooks CountyBryan CountyBulloch CountyBurke CountyButts CountyCalhoun CountyCamden CountyCandler CountyCarroll CountyCatoosa CountyCharlton CountyChatham CountyChattahoochee CountyChattooga CountyCherokee CountyClarke CountyClay CountyClayton CountyClinch CountyCobb CountyCoffee CountyColquitt CountyColumbia CountyCook CountyCoweta CountyCrawford CountyCrisp CountyDade CountyDawson CountyDecatur CountyDeKalb CountyDodge CountyDooly CountyDougherty CountyDouglas CountyEarly CountyEchols CountyEffingham CountyElbert CountyEmanuel CountyEvans CountyFannin CountyFayette CountyFloyd CountyForsyth CountyFranklin CountyFulton CountyGilmer CountyGlascock CountyGlynn CountyGordon CountyGrady CountyGreene CountyGwinnett CountyHabersham CountyHall CountyHancock CountyHaralson CountyHarris CountyHart CountyHeard CountyHenry CountyHouston CountyIrwin CountyJackson CountyJasper CountyJeff Davis CountyJefferson CountyJenkins CountyJohnson CountyJones CountyLamar CountyLanier CountyLaurens CountyLee CountyLiberty CountyLincoln CountyLong CountyLowndes CountyLumpkin CountyMacon CountyMadison CountyMarion CountyMcDuffie CountyMcIntosh CountyMeriwether CountyMiller CountyMitchell CountyMonroe CountyMontgomery CountyMorgan CountyMurray CountyMuscogee CountyNewton CountyOconee CountyOglethorpe CountyPaulding CountyPeach CountyPickens CountyPierce CountyPike CountyPolk CountyPulaski CountyPutnam CountyQuitman CountyRabun CountyRandolph CountyRichmond CountyRockdale CountySchley CountyScreven CountySeminole CountySpalding CountyStephens CountyStewart CountySumter CountyTalbot CountyTaliaferro CountyTattnall CountyTaylor CountyTelfair CountyTerrell CountyThomas CountyTift CountyToombs CountyTowns CountyTreutlen CountyTroup CountyTurner CountyTwiggs CountyUnion CountyUpson CountyWalker CountyWalton CountyWare CountyWarren CountyWashington CountyWayne CountyWebster CountyWheeler CountyWhite CountyWhitfield CountyWilcox CountyWilkes CountyWilkinson CountyWorth CountyBells Ferry Road data center campus (Marietta) · Approved · 108 MW
Power108MW reported · stated
Floor area347,200sq ft
Site31.4acres
IT load72MW

Who is behind it

ProjectBells Ferry Road data center campus (Marietta)Also: Grindcap Marietta campus
Developer and teamGrind Capital Group (Grindcap) (through MMM Acquisitions LLC)
End userNot found in the recordsNot yet named in any record or credited report we have found.

The record, newest first

  1. The mayor said the 30-day appeal window had passed and the developer had not found a buyer, as residents pressed the council. (Marietta Daily Journal, June 9, 2026; Hoodline, June 4, 2026)

  2. The Marietta City Council approved MMM Acquisitions' plan for two data center buildings, a 4-acre substation and a pond on 31 acres off Bells Ferry Road. (WSB-TV, June 17, 2025; Atlanta News First, June 30, 2025; DatacenterDynamics, June 2025)

Conflicts and open questions

  • Inside the city of Marietta, so Cobb County's unincorporated-area moratorium does not apply.
  • DCD page shows no date; the vote is reported as "this month" (June 2025).
  • Exact council vote date not found; reports say June 2025, 7-0 (DCD, Marietta Daily Journal).

The full record

Status note
Marietta rezoned the site in June 2025; as of June 2026 the developer still needed permits, grading and an on-site substation, and the mayor said no buyer had been found.
Power note
DCD gives 72 MW and 36 MW buildings (108 MW total, 72 MW IT load); Hoodline calls 108 MW the IT load. IT load is 72-108 MW depending on source.