Data center campus · 4810 Stonewall Tell Road, Union City, Fulton County, Georgia

Microsoft Union City campus (Project Steamboat)

Approved as of June 25, 2024

A 324 MW, three-building EdgeConneX campus in Union City with Microsoft as end user; the project won a $75 million Fulton tax abatement in 2024. Also known as: EdgeConneX ATL11-ATL13, Project Steamboat, ATL11, ATL12, ATL13.

Cite← Georgia data centers
Appling CountyAtkinson CountyBacon CountyBaker CountyBaldwin CountyBanks CountyBarrow CountyBartow CountyBen Hill CountyBerrien CountyBibb CountyBleckley CountyBrantley CountyBrooks CountyBryan CountyBulloch CountyBurke CountyButts CountyCalhoun CountyCamden CountyCandler CountyCarroll CountyCatoosa CountyCharlton CountyChatham CountyChattahoochee CountyChattooga CountyCherokee CountyClarke CountyClay CountyClayton CountyClinch CountyCobb CountyCoffee CountyColquitt CountyColumbia CountyCook CountyCoweta CountyCrawford CountyCrisp CountyDade CountyDawson CountyDecatur CountyDeKalb CountyDodge CountyDooly CountyDougherty CountyDouglas CountyEarly CountyEchols CountyEffingham CountyElbert CountyEmanuel CountyEvans CountyFannin CountyFayette CountyFloyd CountyForsyth CountyFranklin CountyFulton CountyGilmer CountyGlascock CountyGlynn CountyGordon CountyGrady CountyGreene CountyGwinnett CountyHabersham CountyHall CountyHancock CountyHaralson CountyHarris CountyHart CountyHeard CountyHenry CountyHouston CountyIrwin CountyJackson CountyJasper CountyJeff Davis CountyJefferson CountyJenkins CountyJohnson CountyJones CountyLamar CountyLanier CountyLaurens CountyLee CountyLiberty CountyLincoln CountyLong CountyLowndes CountyLumpkin CountyMacon CountyMadison CountyMarion CountyMcDuffie CountyMcIntosh CountyMeriwether CountyMiller CountyMitchell CountyMonroe CountyMontgomery CountyMorgan CountyMurray CountyMuscogee CountyNewton CountyOconee CountyOglethorpe CountyPaulding CountyPeach CountyPickens CountyPierce CountyPike CountyPolk CountyPulaski CountyPutnam CountyQuitman CountyRabun CountyRandolph CountyRichmond CountyRockdale CountySchley CountyScreven CountySeminole CountySpalding CountyStephens CountyStewart CountySumter CountyTalbot CountyTaliaferro CountyTattnall CountyTaylor CountyTelfair CountyTerrell CountyThomas CountyTift CountyToombs CountyTowns CountyTreutlen CountyTroup CountyTurner CountyTwiggs CountyUnion CountyUpson CountyWalker CountyWalton CountyWare CountyWarren CountyWashington CountyWayne CountyWebster CountyWheeler CountyWhite CountyWhitfield CountyWilcox CountyWilkes CountyWilkinson CountyWorth CountyMicrosoft Union City campus (Project Steamboat) · Approved · 324 MW
Power324MW reported · stated
Floor area2,100,000sq ft
Site136acres

Who is behind it

ProjectMicrosoft Union City campus (Project Steamboat)Also: EdgeConneX ATL11-ATL13, Project Steamboat, ATL11, ATL12, ATL13
Developer and teamEdgeConneX
TA Realty
Burr Computer Environments (site developer)
End userMicrosoft

The record, newest first

  1. EdgeConneX's Atlanta data sheet listed ATL11-ATL13 in Union City as a 202 MW block still to be completed. (EdgeConneX, July 1, 2026)

  2. Trade press placed the 63-acre site in Union City, reported $75 million in Fulton development-authority incentives and named Microsoft as the reported user. (CommercialSearch, July 19, 2024)

  3. Planning documents showed a 2.1 million sq ft, 324 MW campus with Microsoft as end user and a first phase due in 2026. (The Atlanta Journal-Constitution, July 17, 2024; Data Center Frontier, July 18, 2024)

  4. TA Realty and EdgeConneX announced a 324 MW hyperscale campus in metro Atlanta, with TA Digital Group handling power, zoning and permits and EdgeConneX handling design, construction and operations. (Business Wire (TA Realty / EdgeConneX), July 16, 2024)

  5. Develop Fulton voted 5-3 for a $75 million, 10-year tax abatement for the $1.8 billion Stonewall Tell Road project. (The Atlanta Journal-Constitution, June 25, 2024)

  6. Microsoft bought about 136 acres near South Fulton Parkway for data centers. (The Atlanta Journal-Constitution, April 16, 2024)

Conflicts and open questions

  • Land price differs: $52.5 million (AJC, deeds) vs $53.5 million (DCF).
  • Build status after 2024 not confirmed in a citable source; a tracker lists it under construction for 2027.
  • Distinct from the Palmetto/East Point campus in microsoft-east-us-3.
  • (folded from duplicate record edgeconnex-ta-union-city) MW figure differs: 324 MW at announcement vs. 202 MW in the operator's 2026 data sheet.
  • (folded from duplicate record edgeconnex-ta-union-city) Data sheet date is the month in its URL path (2026-07).
  • CommercialSearch described a site of nearly 63 acres, versus about 136 acres in AJC and Data Center Frontier; acres kept at 136.
  • Possible overlap: the AJC placed this tract close to Microsoft's Palmetto campus, which is in existing record microsoft-east-us-3; editor should confirm it is not counted twice.

The full record

Status note
The Development Authority of Fulton County had approved incentives by July 2024; EdgeConneX's 2026 data sheet still lists the three buildings as not yet complete.
Power note
Announced at 324 MW in 2024; EdgeConneX's Q1 2026 data sheet lists 202 MW for ATL11-ATL13 combined.
Evidence
News reports; primary records not yet obtained
Size class
50 MW or more (tracker scope)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.