PCC-DeKalb data center (Ellenwood)
A data center campus with an outdoor substation on about 96 residentially zoned acres in Ellenwood that DeKalb commissioners rejected after staff and the planning commission recommended denial. Also known as: Project Preserve.
Who is behind it
The record, newest first
The Board of Commissioners rejected the permit. (Capital B News Atlanta, Aug. 18, 2026)
Planning staff again recommended denial; the community council had asked for a two-cycle deferral so the moratorium could lapse and new rules pass. (DeKalb County Department of Planning and Sustainability, July 1, 2026)
Commissioners put off a vote until the summer while the county wrote data center rules; staff had recommended denial because the land is zoned residential. (Atlanta News First, Jan. 13, 2026)
The DeKalb Planning Commission recommended denial of the special land use permit, 7-1. (DeKalb County Department of Planning and Sustainability, July 1, 2026)
Conflicts and open questions
- Size differs: the applicant's May 2026 conditions cap buildings at 1.05 million sq ft; news reports describe 2 million sq ft.
- The application predates DeKalb's July 2025 moratorium; the moratorium is cited in the community council's deferral request, but the denial rests on zoning and the comprehensive plan.
- Vote count on Aug. 13, 2026 not found.
- The applicant filed a constitutional-objections letter with the application, preserving a challenge to any denial; no suit over this denial was found in the sources opened.
The full record
- Status note
- DeKalb commissioners rejected the special land use permit on Aug. 13, 2026.
- Evidence
- Primary public records
- Size class
- Under 50 MW (outside main scope; kept for completeness)