Project Arrowhead

Approved as of May 20, 2026

A 1.25 GW, 4.2 million sq ft campus on about 1,066 acres in rural Irwin County that commissioners approved by special exception in May 2026.

Cite← Georgia data centers
Appling CountyAtkinson CountyBacon CountyBaker CountyBaldwin CountyBanks CountyBarrow CountyBartow CountyBen Hill CountyBerrien CountyBibb CountyBleckley CountyBrantley CountyBrooks CountyBryan CountyBulloch CountyBurke CountyButts CountyCalhoun CountyCamden CountyCandler CountyCarroll CountyCatoosa CountyCharlton CountyChatham CountyChattahoochee CountyChattooga CountyCherokee CountyClarke CountyClay CountyClayton CountyClinch CountyCobb CountyCoffee CountyColquitt CountyColumbia CountyCook CountyCoweta CountyCrawford CountyCrisp CountyDade CountyDawson CountyDecatur CountyDeKalb CountyDodge CountyDooly CountyDougherty CountyDouglas CountyEarly CountyEchols CountyEffingham CountyElbert CountyEmanuel CountyEvans CountyFannin CountyFayette CountyFloyd CountyForsyth CountyFranklin CountyFulton CountyGilmer CountyGlascock CountyGlynn CountyGordon CountyGrady CountyGreene CountyGwinnett CountyHabersham CountyHall CountyHancock CountyHaralson CountyHarris CountyHart CountyHeard CountyHenry CountyHouston CountyIrwin CountyJackson CountyJasper CountyJeff Davis CountyJefferson CountyJenkins CountyJohnson CountyJones CountyLamar CountyLanier CountyLaurens CountyLee CountyLiberty CountyLincoln CountyLong CountyLowndes CountyLumpkin CountyMacon CountyMadison CountyMarion CountyMcDuffie CountyMcIntosh CountyMeriwether CountyMiller CountyMitchell CountyMonroe CountyMontgomery CountyMorgan CountyMurray CountyMuscogee CountyNewton CountyOconee CountyOglethorpe CountyPaulding CountyPeach CountyPickens CountyPierce CountyPike CountyPolk CountyPulaski CountyPutnam CountyQuitman CountyRabun CountyRandolph CountyRichmond CountyRockdale CountySchley CountyScreven CountySeminole CountySpalding CountyStephens CountyStewart CountySumter CountyTalbot CountyTaliaferro CountyTattnall CountyTaylor CountyTelfair CountyTerrell CountyThomas CountyTift CountyToombs CountyTowns CountyTreutlen CountyTroup CountyTurner CountyTwiggs CountyUnion CountyUpson CountyWalker CountyWalton CountyWare CountyWarren CountyWashington CountyWayne CountyWebster CountyWheeler CountyWhite CountyWhitfield CountyWilcox CountyWilkes CountyWilkinson CountyWorth CountyProject Arrowhead · Approved · 1,250 MW
Power1,250MW reported · record
Floor area4,220,000sq ft
Site1,066acres

Who is behind it

ProjectProject Arrowhead
Developer and teamPremier Data Center Development (through Premier Data Center Development, LLC)
End userNot found in the recordsNot yet named in any record or credited report we have found.

The record, newest first

  1. County commissioners approved the special exception at a called meeting; WWALS described the approval as unanimous. (WWALS Watershed Coalition, May 21, 2026)

  2. The Southern Georgia Regional Commission opened comments on the DRI through May 11; its report notes the county zoning code lists data centers as a special-exception use in agricultural, heavy industrial and adult-commercial zones. (Southern Georgia Regional Commission (copy hosted by WWALS Watershed Coalition), April 24, 2026)

  3. The county submitted DRI 4689 for the project to the state. (WWALS Watershed Coalition, April 11, 2026; DatacenterDynamics, April 2026)

Conflicts and open questions

  • DRI figures are internally inconsistent: 1,066 acres in the notice vs about 1,205 acres across six parcels; cost written as '$600,000,000 ($6 billion)'; a 30,000 MW daily figure that looks like an error; 18 buildings in the DRI vs five reported by DCD.
  • DCD (undated, April 2026) reported Georgia Power was doing an energy study, a first phase possible in 2030 and full build-out by 2034; part of the land was earlier in the withdrawn Irwin Forward Tech Park.
  • End user not disclosed; claims of Google are unconfirmed.
  • WWALS is an advocacy group; its posts are used for meeting facts and document copies.

The full record

Power note
Peak demand of 1,250 MW in the DRI 4689 filing.
Evidence
Primary public records
Size class
50 MW or more (tracker scope)