Data center campus · 156 Vann Drive and adjoining parcels, Coosa area west of Rome, next to Coosa Middle School, Floyd County, Georgia

Project Gracie (Coosa)

Approved as of May 27, 2025

A seven-building, roughly 2.4 million sq ft Atlas Development campus on about 200 acres near Coosa schools that Floyd commissioners rezoned to heavy industrial in May 2025. Also known as: Atlas Coosa data center.

Cite← Georgia data centers
Appling CountyAtkinson CountyBacon CountyBaker CountyBaldwin CountyBanks CountyBarrow CountyBartow CountyBen Hill CountyBerrien CountyBibb CountyBleckley CountyBrantley CountyBrooks CountyBryan CountyBulloch CountyBurke CountyButts CountyCalhoun CountyCamden CountyCandler CountyCarroll CountyCatoosa CountyCharlton CountyChatham CountyChattahoochee CountyChattooga CountyCherokee CountyClarke CountyClay CountyClayton CountyClinch CountyCobb CountyCoffee CountyColquitt CountyColumbia CountyCook CountyCoweta CountyCrawford CountyCrisp CountyDade CountyDawson CountyDecatur CountyDeKalb CountyDodge CountyDooly CountyDougherty CountyDouglas CountyEarly CountyEchols CountyEffingham CountyElbert CountyEmanuel CountyEvans CountyFannin CountyFayette CountyFloyd CountyForsyth CountyFranklin CountyFulton CountyGilmer CountyGlascock CountyGlynn CountyGordon CountyGrady CountyGreene CountyGwinnett CountyHabersham CountyHall CountyHancock CountyHaralson CountyHarris CountyHart CountyHeard CountyHenry CountyHouston CountyIrwin CountyJackson CountyJasper CountyJeff Davis CountyJefferson CountyJenkins CountyJohnson CountyJones CountyLamar CountyLanier CountyLaurens CountyLee CountyLiberty CountyLincoln CountyLong CountyLowndes CountyLumpkin CountyMacon CountyMadison CountyMarion CountyMcDuffie CountyMcIntosh CountyMeriwether CountyMiller CountyMitchell CountyMonroe CountyMontgomery CountyMorgan CountyMurray CountyMuscogee CountyNewton CountyOconee CountyOglethorpe CountyPaulding CountyPeach CountyPickens CountyPierce CountyPike CountyPolk CountyPulaski CountyPutnam CountyQuitman CountyRabun CountyRandolph CountyRichmond CountyRockdale CountySchley CountyScreven CountySeminole CountySpalding CountyStephens CountyStewart CountySumter CountyTalbot CountyTaliaferro CountyTattnall CountyTaylor CountyTelfair CountyTerrell CountyThomas CountyTift CountyToombs CountyTowns CountyTreutlen CountyTroup CountyTurner CountyTwiggs CountyUnion CountyUpson CountyWalker CountyWalton CountyWare CountyWarren CountyWashington CountyWayne CountyWebster CountyWheeler CountyWhite CountyWhitfield CountyWilcox CountyWilkes CountyWilkinson CountyWorth CountyProject Gracie (Coosa) · Approved
PowerNot statedNot reported in the records found
Floor area2,395,000sq ft
Site200acres

Who is behind it

ProjectProject Gracie (Coosa)Also: Atlas Coosa data center
Developer and teamAtlas Development
End userNot found in the recordsNot yet named in any record or credited report we have found.

The record, newest first

  1. Floyd commissioners approved rezoning 156 Vann Drive and adjoining parcels from suburban residential to heavy industrial, limited to data center use, with lighting and noise limits, a 100-foot undisturbed buffer and the 200-foot southern buffer kept. (WRGA News, May 27, 2025; Floyd County Board of Commissioners, May 27, 2025)

  2. A regional-impact filing (DRI 4448) described seven buildings and about 2.4 million sq ft, finished by December 2032; the Rome-Floyd planning commission recommended approval. (Bisnow, May 5, 2025; Georgia Department of Community Affairs, Oct. 30, 2026)

Conflicts and open questions

  • The planning commission vote is reported as 4-3 (Bisnow) but shown as 5-2 on the county agenda.
  • The commissioners' vote count could not be confirmed (minutes link returned 404).
  • MW not stated; acreage (about 200) is from Bisnow.
  • The site is described as next to Coosa Middle School (Bisnow) and near Coosa High School (WRGA).
  • The current landowner is described as a family living trust; not named here. WRGA reported the land was sold by the Floyd County Board of Education.

The full record

Evidence
News reports; primary records not yet obtained
Size class
50 MW or more (tracker scope)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.