QTS Augusta campus (Gordon Highway)
A six-building, roughly 2.2 million sq ft QTS campus on Gordon Highway near Fort Gordon that began as T5@Augusta, was rezoned in 2022 and expanded in 2024, and is not covered by Augusta's 2026 data center ordinance. Also known as: Project Eisenhower, T5@Augusta.
Who is behind it
Eagle South LLC (earlier applicant) (through Eagle South LLC)
T5 Data Centers (original developer, no longer involved)
The record, newest first
When adopting a new data center ordinance, city officials said it did not apply to the QTS project, whose zoning predated the moratorium and whose site plan was already approved. (WRDW/WAGT, Sept. 15, 2026)
At a second community meeting, QTS said it had applied for an Army Corps of Engineers permit for impacts to aquatic resources and that steps after its purchase included a height variance. (WRDW/WAGT, June 24, 2026; QTS Data Centers, Oct. 30, 2026)
QTS presented the project to the Augusta Commission, citing about $2 billion in investment and 160 to 220 permanent jobs. (The Augusta Press, Feb. 4, 2026)
Richmond County approved the expanded six-building plan for Eagle South LLC after a second regional-impact review. (The Augusta Press, Dec. 28, 2025)
The land was rezoned from agricultural and manufactured-home residential to general business for the original T5 project of four two-story buildings. (The Augusta Press, Dec. 28, 2025)
Conflicts and open questions
- The 2022 rezoning date is given as a year only (2022-01-01 placeholder) and the 2024 approval as a month (June 2024, 2024-06-01 placeholder).
- QTS does not disclose MW for security reasons; no MW is recorded here.
- Floor area is reported as almost 2.2 million sq ft (Augusta Press, Feb. 2026) and as more than 1.4 million sq ft (Augusta Press, Dec. 2025); the larger figure is the more recent.
- The Augusta Press gives the tract as '163' without a unit; acreage is left blank.
- QTS's page says the first building is expected in spring 2028; the QTS page is undated and is cited with the access date 2026-10-30.
- WRDW called the site 'under construction' in Sept. 2026, while the QTS page says further approvals are still required; status reflects the city staff account.
- QTS's page says zoning approvals came in 2022, 2024 and 2025.
The full record
- Status note
- City staff said the site plan was approved and foundation plans had been submitted; QTS's own page still described further city and state approvals as pending.
- Evidence
- News reports; primary records not yet obtained
- Size class
- Under 50 MW (outside main scope; kept for completeness)