QTS Blakely campus
QTS's proposed 12 million sq ft, up to 1.5 GW campus near Blakely in southwest Georgia, backed by a $28.75 million community agreement signed in August 2026.
Who is behind it
The record, newest first
Blakely and Early County leaders signed an agreement creating a betterment fund of at least $28.75 million; construction could start mid-2027. (WTVY, Aug. 14, 2026)
AJC reported plans for up to nine data center buildings and three substations on land owned by a McKnight Engler affiliate, with completion targeted for 2035. (The Atlanta Journal-Constitution, March 13, 2026)
A DRI was filed for QTS's Blakely data center campus of up to 12 million sq ft, with 1,500 MW listed pending utility studies. (Georgia Department of Community Affairs, March 10, 2026; Georgia Department of Community Affairs, March 10, 2026; Georgia Department of Community Affairs, Oct. 30, 2026)
Conflicts and open questions
- Agreement signing date: WTVY (Aug. 14, 2026) says it was signed Thursday, i.e. Aug. 13, 2026.
- Some residents raised water and utility-cost concerns (WTVY).
- Campus acreage not stated; the landowner affiliate holds more than 2,332 acres around the airport (AJC).
- DRI lists Georgia Power as energy supplier.
The full record
- Status note
- DRI filed; city and county leaders signed a community agreement with QTS; rezoning and site-plan steps remained.
- Power note
- DRI lists 1,500 MW pending completed utility studies.
- Evidence
- Primary public records
- Size class
- 50 MW or more (tracker scope)