Data center campus · South of GA 20 West and east of Rocky Creek Road, between McDonough and Hampton, Henry County, Georgia

Rocky Creek Road data center (Red Wolf)

Proposed as of Jan. 6, 2025

A roughly 1.25 million sq ft data center with its own substation proposed on about 148 acres off GA 20 in western Henry County, which the zoning board recommended in 2024. Also known as: 0 Rocky Creek, DRI 4198.

Cite← Georgia data centers
Appling CountyAtkinson CountyBacon CountyBaker CountyBaldwin CountyBanks CountyBarrow CountyBartow CountyBen Hill CountyBerrien CountyBibb CountyBleckley CountyBrantley CountyBrooks CountyBryan CountyBulloch CountyBurke CountyButts CountyCalhoun CountyCamden CountyCandler CountyCarroll CountyCatoosa CountyCharlton CountyChatham CountyChattahoochee CountyChattooga CountyCherokee CountyClarke CountyClay CountyClayton CountyClinch CountyCobb CountyCoffee CountyColquitt CountyColumbia CountyCook CountyCoweta CountyCrawford CountyCrisp CountyDade CountyDawson CountyDecatur CountyDeKalb CountyDodge CountyDooly CountyDougherty CountyDouglas CountyEarly CountyEchols CountyEffingham CountyElbert CountyEmanuel CountyEvans CountyFannin CountyFayette CountyFloyd CountyForsyth CountyFranklin CountyFulton CountyGilmer CountyGlascock CountyGlynn CountyGordon CountyGrady CountyGreene CountyGwinnett CountyHabersham CountyHall CountyHancock CountyHaralson CountyHarris CountyHart CountyHeard CountyHenry CountyHouston CountyIrwin CountyJackson CountyJasper CountyJeff Davis CountyJefferson CountyJenkins CountyJohnson CountyJones CountyLamar CountyLanier CountyLaurens CountyLee CountyLiberty CountyLincoln CountyLong CountyLowndes CountyLumpkin CountyMacon CountyMadison CountyMarion CountyMcDuffie CountyMcIntosh CountyMeriwether CountyMiller CountyMitchell CountyMonroe CountyMontgomery CountyMorgan CountyMurray CountyMuscogee CountyNewton CountyOconee CountyOglethorpe CountyPaulding CountyPeach CountyPickens CountyPierce CountyPike CountyPolk CountyPulaski CountyPutnam CountyQuitman CountyRabun CountyRandolph CountyRichmond CountyRockdale CountySchley CountyScreven CountySeminole CountySpalding CountyStephens CountyStewart CountySumter CountyTalbot CountyTaliaferro CountyTattnall CountyTaylor CountyTelfair CountyTerrell CountyThomas CountyTift CountyToombs CountyTowns CountyTreutlen CountyTroup CountyTurner CountyTwiggs CountyUnion CountyUpson CountyWalker CountyWalton CountyWare CountyWarren CountyWashington CountyWayne CountyWebster CountyWheeler CountyWhite CountyWhitfield CountyWilcox CountyWilkes CountyWilkinson CountyWorth CountyRocky Creek Road data center (Red Wolf) · Proposed
PowerNot statedNot reported in the records found
Floor area1,253,752sq ft
Site148.2acres

Who is behind it

ProjectRocky Creek Road data center (Red Wolf)Also: 0 Rocky Creek, DRI 4198
Developer and teamRed Wolf DCD Properties (through Red Wolf DCD Properties, LLC)
0 Rocky Creek Road, LLC (applicant and owner) (through 0 Rocky Creek Road, LLC)
End userNot found in the recordsNot yet named in any record or credited report we have found.

The record, newest first

  1. The county held a town hall on this proposal and the Simpson Mill Road data center. (The Henry Reporter, Jan. 3, 2025)

  2. The commissioners' scheduled hearing was postponed to a 2025 meeting. (The Henry Reporter, Nov. 13, 2024)

  3. Henry's zoning advisory board recommended approval of the land-use change and rezoning from RA to OI, reportedly on a 3-2 vote. (The Henry Reporter, Nov. 13, 2024; 11Alive, Nov. 15, 2024; WSB-TV, Nov. 15, 2024)

  4. Henry County submitted DRI 4198 for a 1,253,752 sq ft data center at the southeast corner of Rocky Creek Road and GA 20 West, with Red Wolf DCD Properties as developer and completion targeted for 2028. (Georgia Department of Community Affairs, May 3, 2024; Georgia Department of Community Affairs, May 3, 2024; Georgia Department of Community Affairs, Oct. 30, 2026; Southern Business & Development, Aug. 8, 2024; DatacenterDynamics, May 2024)

Conflicts and open questions

  • Cases COMP-AM-24-02 and RZ-24-07; state DRI 4198 (submitted May 3, 2024).
  • WSB-TV's early report suggested the opposite outcome for the two Henry sites; The Henry Reporter and 11Alive both say Rocky Creek was recommended for approval and the Simpson Mill/Strickland site for denial.
  • Henry County final decision not found; The Henry Reporter suspended operations in June 2025. Status needs a check of Henry County BOC minutes.
  • Owner/applicant name varies: 0 Rocky Creek Road, LLC (Henry Reporter), 0 Rocky Creek, LLC (DRI), Rocky Creek, LLC (WSB-TV).
  • DCD article is undated as fetched; the May 2024 date is approximate.
  • The 3-2 vote count comes from 11Alive only.

The full record

Status note
The zoning advisory board recommended approval in November 2024; the commissioners' vote was postponed to an unscheduled 2025 meeting, and no later decision was found.
Evidence
Primary public records
Size class