Data center campus · 11760 Panhandle Road, Lovejoy, Clayton County, Georgia

Stillwater Technology Park

Withdrawn as of Aug. 6, 2026

A 15-building, 1.25 GW data center campus proposed on about 400 acres on Panhandle Road in Lovejoy near two schools, withdrawn in August 2026, after which the city banned data centers.

Cite← Georgia data centers
Appling CountyAtkinson CountyBacon CountyBaker CountyBaldwin CountyBanks CountyBarrow CountyBartow CountyBen Hill CountyBerrien CountyBibb CountyBleckley CountyBrantley CountyBrooks CountyBryan CountyBulloch CountyBurke CountyButts CountyCalhoun CountyCamden CountyCandler CountyCarroll CountyCatoosa CountyCharlton CountyChatham CountyChattahoochee CountyChattooga CountyCherokee CountyClarke CountyClay CountyClayton CountyClinch CountyCobb CountyCoffee CountyColquitt CountyColumbia CountyCook CountyCoweta CountyCrawford CountyCrisp CountyDade CountyDawson CountyDecatur CountyDeKalb CountyDodge CountyDooly CountyDougherty CountyDouglas CountyEarly CountyEchols CountyEffingham CountyElbert CountyEmanuel CountyEvans CountyFannin CountyFayette CountyFloyd CountyForsyth CountyFranklin CountyFulton CountyGilmer CountyGlascock CountyGlynn CountyGordon CountyGrady CountyGreene CountyGwinnett CountyHabersham CountyHall CountyHancock CountyHaralson CountyHarris CountyHart CountyHeard CountyHenry CountyHouston CountyIrwin CountyJackson CountyJasper CountyJeff Davis CountyJefferson CountyJenkins CountyJohnson CountyJones CountyLamar CountyLanier CountyLaurens CountyLee CountyLiberty CountyLincoln CountyLong CountyLowndes CountyLumpkin CountyMacon CountyMadison CountyMarion CountyMcDuffie CountyMcIntosh CountyMeriwether CountyMiller CountyMitchell CountyMonroe CountyMontgomery CountyMorgan CountyMurray CountyMuscogee CountyNewton CountyOconee CountyOglethorpe CountyPaulding CountyPeach CountyPickens CountyPierce CountyPike CountyPolk CountyPulaski CountyPutnam CountyQuitman CountyRabun CountyRandolph CountyRichmond CountyRockdale CountySchley CountyScreven CountySeminole CountySpalding CountyStephens CountyStewart CountySumter CountyTalbot CountyTaliaferro CountyTattnall CountyTaylor CountyTelfair CountyTerrell CountyThomas CountyTift CountyToombs CountyTowns CountyTreutlen CountyTroup CountyTurner CountyTwiggs CountyUnion CountyUpson CountyWalker CountyWalton CountyWare CountyWarren CountyWashington CountyWayne CountyWebster CountyWheeler CountyWhite CountyWhitfield CountyWilcox CountyWilkes CountyWilkinson CountyWorth CountyStillwater Technology Park · Withdrawn · 1,250 MW
Power1,250MW reported · record
Floor area3,465,000sq ft
Site400acres

Who is behind it

ProjectStillwater Technology Park
Developer and teamStillwater Development, LLC
End userNot found in the recordsNot yet named in any record or credited report we have found.

The record, newest first

  1. Lovejoy adopted an ordinance barring data centers anywhere in the city, following opposition to this proposal. (Atlanta News First, Sept. 29, 2026)

  2. The developer formally withdrew the application at a special council session called for that purpose; the city had cited school traffic on Panhandle Road in the regional review, and DCA lists the DRI as withdrawn. (Atlanta News First, Aug. 6, 2026; Georgia Department of Community Affairs, July 22, 2026; Georgia Department of Community Affairs, Oct. 30, 2026)

  3. Trade press reported a regional-impact filing for up to 15 buildings and 3.47 million sq ft, with a 1.25 GW Central Georgia EMC connection. (Baxtel, July 27, 2026)

  4. A DRI was logged for about 3.47 million sq ft of data center buildings at 11760 Panhandle Road, with a stated 1,250 MW load. (Georgia Department of Community Affairs, July 22, 2026; Georgia Department of Community Affairs, July 22, 2026; Georgia Department of Community Affairs, Oct. 30, 2026)

  5. Stillwater Development first filed plans with the city (month only; reported by Atlanta News First). (Atlanta News First, Aug. 6, 2026)

Conflicts and open questions

  • Acreage (400) is from Baxtel; the DRI gives only building area.
  • Lovejoy ban vote date inferred as Monday, Sept. 28, 2026 from an article dated Tuesday, Sept. 29.
  • Some trackers place 'Stillwater' buildings in Hampton (Henry County); not verified as the same campus.
  • Lovejoy is outside Clayton County's moratorium; the city later banned data centers (already in ga_moratoriums.json).
  • The DRI form says part of the project lies in Henry County.

The full record

Status note
Withdrawn at a special Lovejoy City Council session; the mayor said the owners now plan housing on the site.
Power note
DRI lists 1,250 MW as the developer's own figure; news reports give 1.25 GW.
Evidence
Primary public records
Size class
50 MW or more (tracker scope)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.