Data center campus · Palmetto area of south Fulton; earlier Fairburn filing was off I-85 and Gullatt Road, Fulton County, Georgia

T5 ATL IV campus (Palmetto/Fairburn)

Proposed as of Aug. 28, 2024

A T5 Data Centers campus planned on 91 acres near Palmetto that the company says can grow to 300 MW; an earlier 2024 Fairburn filing along Gullatt Road was withdrawn. Also known as: T5@Atlanta IV.

Cite← Georgia data centers
Appling CountyAtkinson CountyBacon CountyBaker CountyBaldwin CountyBanks CountyBarrow CountyBartow CountyBen Hill CountyBerrien CountyBibb CountyBleckley CountyBrantley CountyBrooks CountyBryan CountyBulloch CountyBurke CountyButts CountyCalhoun CountyCamden CountyCandler CountyCarroll CountyCatoosa CountyCharlton CountyChatham CountyChattahoochee CountyChattooga CountyCherokee CountyClarke CountyClay CountyClayton CountyClinch CountyCobb CountyCoffee CountyColquitt CountyColumbia CountyCook CountyCoweta CountyCrawford CountyCrisp CountyDade CountyDawson CountyDecatur CountyDeKalb CountyDodge CountyDooly CountyDougherty CountyDouglas CountyEarly CountyEchols CountyEffingham CountyElbert CountyEmanuel CountyEvans CountyFannin CountyFayette CountyFloyd CountyForsyth CountyFranklin CountyFulton CountyGilmer CountyGlascock CountyGlynn CountyGordon CountyGrady CountyGreene CountyGwinnett CountyHabersham CountyHall CountyHancock CountyHaralson CountyHarris CountyHart CountyHeard CountyHenry CountyHouston CountyIrwin CountyJackson CountyJasper CountyJeff Davis CountyJefferson CountyJenkins CountyJohnson CountyJones CountyLamar CountyLanier CountyLaurens CountyLee CountyLiberty CountyLincoln CountyLong CountyLowndes CountyLumpkin CountyMacon CountyMadison CountyMarion CountyMcDuffie CountyMcIntosh CountyMeriwether CountyMiller CountyMitchell CountyMonroe CountyMontgomery CountyMorgan CountyMurray CountyMuscogee CountyNewton CountyOconee CountyOglethorpe CountyPaulding CountyPeach CountyPickens CountyPierce CountyPike CountyPolk CountyPulaski CountyPutnam CountyQuitman CountyRabun CountyRandolph CountyRichmond CountyRockdale CountySchley CountyScreven CountySeminole CountySpalding CountyStephens CountyStewart CountySumter CountyTalbot CountyTaliaferro CountyTattnall CountyTaylor CountyTelfair CountyTerrell CountyThomas CountyTift CountyToombs CountyTowns CountyTreutlen CountyTroup CountyTurner CountyTwiggs CountyUnion CountyUpson CountyWalker CountyWalton CountyWare CountyWarren CountyWashington CountyWayne CountyWebster CountyWheeler CountyWhite CountyWhitfield CountyWilcox CountyWilkes CountyWilkinson CountyWorth CountyT5 ATL IV campus (Palmetto/Fairburn) · Proposed · 300 MW
Power300MW reported · stated
Site91acres

Who is behind it

ProjectT5 ATL IV campus (Palmetto/Fairburn)Also: T5@Atlanta IV
Developer and teamT5 Data Centers
End userNot found in the recordsNot yet named in any record or credited report we have found.

The record, newest first

  1. T5 announced it had acquired a 91-acre Palmetto site zoned for data center use, scalable to 300 MW, with an on-site substation expected in 2026. (PR Newswire (T5 Data Centers), Aug. 28, 2024)

  2. The Fairburn regional-impact filing (DRI 4222) was withdrawn, according to the state DRI record. (Georgia Department of Community Affairs, Oct. 30, 2026)

  3. T5 filed a regional-impact application for two two-story buildings of about 495,000 sq ft off I-85 and Gullatt Road at Fairburn's southern edge. (Bisnow, June 12, 2024; The Atlanta Journal-Constitution, June 14, 2024; Georgia Department of Community Affairs, Oct. 30, 2026)

Conflicts and open questions

  • Opened records do not state outright that the 91-acre Palmetto tract and the Gullatt Road Fairburn filing are the same parcel; DatacenterDynamics coverage (undated on fetch) describes a later ATL IV regional-impact filing on Gullatt Road for three buildings and up to 1.32 million sq ft, but it was not cited because no publication date could be read.
  • No tenant is named. Microsoft's Palmetto project is tracked separately as microsoft-east-us-3.

The full record

Status note
T5 says it closed on a 91-acre site already zoned for data centers; no construction start has been confirmed in an opened record.
Power note
Developer says the campus can scale to as much as 300 MW.
Evidence
News reports; primary records not yet obtained
Size class
50 MW or more (tracker scope)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.