Vantage Westlake campus (Plummer Road)
A Vantage Data Centers campus of about 754,000 sq ft west of Plummer Road in South Fulton, now under construction, with a 2026 request to rezone more land beside it. Also known as: Vantage GA2.
Who is behind it
The record, newest first
A Vantage entity asked South Fulton to rezone parcels at 6585 and 6605 Plummer Road and Riverside Drive from SUB-A to M-1 (case Z26-003) to join them with the data center site to the north. (City of South Fulton, Feb. 2, 2026)
The Atlanta Regional Commission issued its finding on the Westlake review. (Georgia Department of Community Affairs, Oct. 30, 2026)
Trade press reported completion targeted for January 2028. (Inside Towers, Aug. 16, 2024)
Vantage filed a regional-impact review (DRI 4256, "Westlake") for about 754,000 sq ft of data center space between Plummer Road and Riverside Drive. (Georgia Department of Community Affairs, Oct. 30, 2026; The Atlanta Journal-Constitution, Aug. 20, 2024; Bisnow, Aug. 15, 2024)
Conflicts and open questions
- Power and acreage not reported in opened sources; kept because construction is under way. Size versus the 50 MW floor is unknown.
- An AI-generated civic-meeting summary (Sept. 2025) described a South Fulton Development Authority bond inducement for 'Project DONES', two hyperscale and two colocation data centers on Plummer and Stacks roads worth $2.3 billion; not cited because it is not an official or bylined record.
- The rezoning agenda does not name the project under construction to the north; linking it to DRI 4256 is an inference from location.
The full record
- Status note
- Vantage's rezoning application says the parcels to the north are under construction for a data center.
- Evidence
- Primary public records
- Size class
- Under 50 MW (outside main scope; kept for completeness)