St. Louis (city)
5 projects on record · 1 moratorium or ban action
← Statewide map| Armory Innovation District data center | Contour; TeraWatt; THO Investments; Steadfast City; ARCO | 120 | Approved | April 21, 2026 | 50 MW+ |
| TierPoint St. Louis - Locust | TierPoint | 5 | Operating | Oct. 23, 2026 | Under 50 MW |
| 210 North Tucker carrier hotel (Netrality St. Louis) | Netrality Data Centers | — | Operating | Oct. 23, 2026 | Under 50 MW |
| 900 Walnut data center (Netrality St. Louis) | Netrality Data Centers | — | Operating | Oct. 23, 2026 | Under 50 MW |
| TierPoint St. Louis - Olive | TierPoint | — | Operating | Oct. 23, 2026 | Under 50 MW |
Moratoriums and bans
- Sept. 17, 2026 St. Louis: Zoning ordinance. After declining a moratorium in Sept. 2025 in favor of a mayoral framework, the city adopted Ordinance 72181 (Board Bill 49), adding data center zoning regulations as Section 26.77, effective Sept. 17, 2026. (City of St. Louis, Sept. 17, 2026; St. Louis Public Radio, Sept. 18, 2025)
Updates, newest first
- Oct. 23, 2026 210 North Tucker carrier hotel (Netrality St. Louis) · Netrality's page lists 442,000 sq ft of colocation space, 61 or more on-net network providers and four peering exchanges at the building. (Netrality Data Centers, Oct. 23, 2026)
- Oct. 23, 2026 900 Walnut data center (Netrality St. Louis) · Netrality's page lists 120,000 sq ft of colocation space and 56 or more on-net network providers at 900 Walnut. (Netrality Data Centers, Oct. 23, 2026)
- Oct. 23, 2026 TierPoint St. Louis - Locust · TierPoint's location page lists the site as available, with 135,840+ sq ft and four 2 MW backup generators. (TierPoint, Oct. 23, 2026)
- Oct. 23, 2026 TierPoint St. Louis - Olive · TierPoint's location page lists the site as available, with 11,000+ sq ft of raised floor. (TierPoint, Oct. 23, 2026)
- Sept. 17, 2026 St. Louis: Zoning ordinance · After declining a moratorium in Sept. 2025 in favor of a mayoral framework, the city adopted Ordinance 72181 (Board Bill 49), adding data center zoning regulations as Section 26.77, effective Sept. 17, 2026. (City of St. Louis, Sept. 17, 2026; St. Louis Public Radio, Sept. 18, 2025)
- Sept. 11, 2026 Armory Innovation District data center · The Board of Aldermen unanimously passed data center zoning rules (Board Bill 49); the Armory project is not covered and is bound instead by similar conditions in its permit. (St. Louis Public Radio, Sept. 11, 2026)
- Aug. 28, 2026 Armory Innovation District data center · Opponents, including the Eco-Socialist Green Party of Eastern Missouri, filed suit asking a court to reverse the Board of Adjustment's denial of their appeals and to stay the permit; they allege the decision was arbitrary and the process rushed. The city said it does not comment on pending litigation. (St. Louis Public Radio, Aug. 29, 2026; St. Louis Public Radio, Sept. 11, 2026)
- April 21, 2026 Armory Innovation District data center · The Board of Public Service voted unanimously for the conditional use permit, with conditions on cooling, renewable energy and community benefits. (The St. Louis American, April 21, 2026; The Labor Tribune, April 30, 2026)
- Feb. 25, 2026 Armory Innovation District data center · A revised plan moved the 120 MW data center to the neighboring Macy's/Famous-Barr warehouse site and would turn the Armory into offices; a zoning hearing was set for March 19. (St. Louis Public Radio, Feb. 25, 2026)
- Sept. 25, 2025 Armory Innovation District data center · STLPR reported documents showing a roughly $1.5 billion plan to put a data center in the Armory building and its parking lot at 500 Prospect Ave. (St. Louis Public Radio, Sept. 25, 2025)
- Aug. 16, 2024 TierPoint St. Louis - Locust · St. Louis Magazine reported phase one was expected in the second half of 2025. (St. Louis Magazine, Aug. 16, 2024)
- Aug. 13, 2024 TierPoint St. Louis - Locust · TierPoint announced it had bought the building and would invest up to $150 million, starting with 22,600 sq ft of data center space. (TierPoint, Aug. 13, 2024; DCD, Aug. 14, 2024)
- June 2, 2023 210 North Tucker carrier hotel (Netrality St. Louis) · DCD reported that Cybercon, owned by Edge Centres, runs space inside a Netrality building in St. Louis (the building is not named). (DatacenterDynamics, June 2, 2023)
- June 22, 2022 210 North Tucker carrier hotel (Netrality St. Louis) · Netrality opened two new data halls at 210 North Tucker, adding about 11,600 sq ft and roughly 1.2 MW of critical capacity. (Netrality Data Centers, June 22, 2022; DatacenterDynamics, June 23, 2022)
- July 19, 2016 210 North Tucker carrier hotel (Netrality St. Louis) · Netrality bought 210 N. Tucker and 900 Walnut from Digital Realty, along with the 365 Data Centers colocation facility inside 210 N. Tucker. (DatacenterDynamics, July 19, 2016)
- July 19, 2016 900 Walnut data center (Netrality St. Louis) · Netrality bought 900 Walnut from Digital Realty in the same deal as 210 N. Tucker. (DatacenterDynamics, July 19, 2016)
Statewide
Missouri's data storage center exemption (RSMo 144.810, enacted by S.B. 149 in 2015, revised 2018) waives state and local sales and use tax on utilities, equipment and construction materials for new centers investing $25 million and adding 10 jobs at 150% of the county average wage within 36 months (up to 15 years), or for expansions of $5 million and 5 jobs (up to 10 years), capped at the projected 10-year net fiscal benefit. The revisor shows no amendment since 2018. (Missouri Revisor of Statutes, Aug. 28, 2018; Missouri Independent, June 29, 2026) S.B. 4 (2025) added RSMo 393.130.7, effective Aug. 28, 2025: utilities with more than 250,000 customers must file tariffs for customers expected to reach 100 MW peak demand (50 MW for smaller utilities) so those customers pay their share and other classes do not bear unjust costs; the PSC may extend this to smaller loads. (Missouri Revisor of Statutes, Aug. 28, 2025; Missouri Public Service Commission, 2026) PSC File No. EO-2025-0154 (Evergy Missouri Metro and Evergy Missouri West): the order issued Nov. 13, 2025, effective Dec. 13, 2025, approved the Large Load Power Service plan for loads of 75 MW or more, with a 12-year minimum term plus an optional ramp of up to 5 years, collateral of two years of minimum bills and exit fees; a separate proposal from PSC staff and the Public Counsel was not adopted. (Missouri Public Service Commission (EFIS), Nov. 13, 2025; Missouri Public Service Commission, Nov. 14, 2025; Missouri Independent, Nov. 14, 2025) PSC File No. ET-2025-0184 (Ameren Missouri): the commission unanimously approved a large-load rate plan on Nov. 24, 2025 for customers of 75 MW or more, with a 12-year minimum term, exit fees and optional clean-energy subscription programs; the Consumers Council of Missouri sought rehearing Dec. 3, 2025. (Missouri Public Service Commission (EFIS), Dec. 3, 2025; St. Louis Public Radio, Nov. 24, 2025; Missouri Public Service Commission, 2026) PSC File No. ET-2026-0184 (Liberty Utilities): the large-load tariff case was still in progress, per the PSC fact sheet. (Missouri Public Service Commission, 2026) 2026 session: no data center bill passed. HB 3362 and HB 3364 (large-load cost recovery and DNR permits for water use above 2 million gallons a day) got a House committee hearing in March 2026 (HB 3362 on March 30) but no vote; HB 3390 (hyperscale limits, Rep. Cupps) and HB 2239 (low-water cooling for 100 MW centers, Rep. Murray) got no hearing. Missouri has no state data center moratorium or siting law. (Missouri House of Representatives, March 30, 2026; St. Louis Public Radio, Feb. 26, 2026; Missouri Independent (from Columbia Missourian), June 5, 2026; St. Louis Public Radio, June 29, 2026; Missouri Coalition for the Environment, May 20, 2026) Missouri data centers →