Data center project · Storey County, Nevada
Google data center, Tahoe-Reno Industrial Center
Operating · Google's operating Storey County campus, approved for state abatements in 2020 and served in part through NV Energy's Clean Transition Tariff for Fervo geothermal power.
- Status
- Operating · as of May 2025
- Location
- Tahoe-Reno Industrial Center · Storey County
- Power
- Not reported
No power figure in the sources reviewed. - Developer and team
- Google (Design, LLC)
- Utility
- NV Energy (Sierra Pacific Power)
- Incentives
- GOED approved 20-year abatements Sept. 16, 2020: a 2% sales tax rate (estimated $16.8 million) and a 75% personal property tax abatement (estimated $8.25 million), shown separately.
- Evidence
- Primary public records
- Size class
- Under 50 MW (outside main scope; kept for completeness)
Updates, newest first
- Sept. 15, 2026 The Indy reported the 2020 approval had come up in a Reno mayoral campaign ad and noted the board then had no discretion to refuse. (The Nevada Independent, Sept. 15, 2026)
- May 19, 2025 ThinkGeoEnergy reported the PUCN approved the tariff, routing 115 MW of Fervo geothermal power to Google's data centers. (ThinkGeoEnergy, May 19, 2025)
- June 7, 2024 NV Energy and Google filed for approval of an energy supply agreement that would let Google's Nevada data centers take service under the Clean Transition Tariff proposed in docket 24-05023. (American Public Power Association, June 16, 2024; Utility Dive, June 21, 2024)
- Sept. 16, 2020 The GOED board approved 20-year abatements for Google (Design, LLC) for a $600 million data center in the industrial center expected to employ at least 50 people: a sales tax abatement estimated at $16.8 million and a personal property tax abatement estimated at $8.25 million. (Governor's Office of Economic Development, Sept. 16, 2020)
Conflicts and open questions
- The two abatement estimates cover different taxes and are not added together here.
Have records about this project? Send them to tips@signaldata.org.