Data center campus · Unincorporated Tulsa County west of Owasso, between E. 76th and E. 86th streets north and N. Yale Ave. and N. Sheridan Road, near Cherokee Industrial Park, Tulsa County, Oklahoma

Google Tulsa County data center campus (Project Clydesdale)

Under construction as of Aug. 20, 2026

A 506-acre campus west of Owasso that Tulsa County rezoned and granted incentives in 2025, now under construction by Beale Infrastructure for Google. Also known as: Project Clydesdale.

Cite← Oklahoma data centers
Adair CountyAlfalfa CountyAtoka CountyBeaver CountyBeckham CountyBlaine CountyBryan CountyCaddo CountyCanadian CountyCarter CountyCherokee CountyChoctaw CountyCimarron CountyCleveland CountyCoal CountyComanche CountyCotton CountyCraig CountyCreek CountyCuster CountyDelaware CountyDewey CountyEllis CountyGarfield CountyGarvin CountyGrady CountyGrant CountyGreer CountyHarmon CountyHarper CountyHaskell CountyHughes CountyJackson CountyJefferson CountyJohnston CountyKay CountyKingfisher CountyKiowa CountyLatimer CountyLe Flore CountyLincoln CountyLogan CountyLove CountyMajor CountyMarshall CountyMayes CountyMcClain CountyMcCurtain CountyMcIntosh CountyMurray CountyMuskogee CountyNoble CountyNowata CountyOkfuskee CountyOklahoma CountyOkmulgee CountyOsage CountyOttawa CountyPawnee CountyPayne CountyPittsburg CountyPontotoc CountyPottawatomie CountyPushmataha CountyRoger Mills CountyRogers CountySeminole CountySequoyah CountyStephens CountyTexas CountyTillman CountyTulsa CountyWagoner CountyWashington CountyWashita CountyWoods CountyWoodward CountyGoogle Tulsa County data center campus (Project Clydesdale) · Under construction
PowerNot statedNot reported in the records found
Floor area800,000sq ft
Site506acres

Who is behind it

ProjectGoogle Tulsa County data center campus (Project Clydesdale)Also: Project Clydesdale
Developer and teamBeale Infrastructure
Google
End userGoogle

The record, newest first

  1. Google said it will operate the campus, with PSO serving it through a new on-site substation funded by Beale. (Tulsa Regional Chamber, Aug. 19, 2026; News 9, Aug. 20, 2026; DatacenterDynamics, Aug. 19, 2026; Google, 2026)

  2. Beale broke ground on the campus, planned as one to four phases of about 200,000 square feet. (DatacenterDynamics, Nov. 3, 2025; Tulsa Regional Chamber, Aug. 19, 2026)

  3. Commissioners unanimously approved Project Clydesdale's plan and incentive districts. (Public Radio Tulsa, Sept. 29, 2025)

  4. Tulsa County commissioners voted 3-0 after a three-hour hearing to rezone the land from agricultural to light industrial; residents raised water, wildlife and grid concerns. (Public Radio Tulsa, July 17, 2025)

Conflicts and open questions

  • No MW figure found. sqft (800,000) is four 200,000 sq ft phases if all are built.
  • The Tulsa Flyer reported that Tulsa's March 2026 city moratorium would not affect Clydesdale, which was already being built; the site is in unincorporated Tulsa County.
  • DCD described the site as on Cherokee Nation land, though the tribe has no direct regulatory control over it.
  • No primary county record was opened; the zoning case number was not found. Investment: at least $700 million per phase in the county plan (PRT); DCD later reported $1 billion.

The full record

Status note
Beale Infrastructure broke ground in late Oct. 2025; Google said in Aug. 2026 it will operate the campus and that construction is underway.
Evidence
Primary public records
Size class
50 MW or more (tracker scope)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.