Data centers · Tulsa County, Oklahoma

Tulsa County

5 projects on record · 2 moratorium or ban actions

← Statewide map
Adair CountyAlfalfa CountyAtoka CountyBeaver CountyBeckham CountyBlaine CountyBryan CountyCaddo CountyCanadian CountyCarter CountyCherokee CountyChoctaw CountyCimarron CountyCleveland CountyCoal CountyComanche CountyCotton CountyCraig CountyCreek CountyCuster CountyDelaware CountyDewey CountyEllis CountyGarfield CountyGarvin CountyGrady CountyGrant CountyGreer CountyHarmon CountyHarper CountyHaskell CountyHughes CountyJackson CountyJefferson CountyJohnston CountyKay CountyKingfisher CountyKiowa CountyLatimer CountyLe Flore CountyLincoln CountyLogan CountyLove CountyMajor CountyMarshall CountyMayes CountyMcClain CountyMcCurtain CountyMcIntosh CountyMurray CountyMuskogee CountyNoble CountyNowata CountyOkfuskee CountyOklahoma CountyOkmulgee CountyOsage CountyOttawa CountyPawnee CountyPayne CountyPittsburg CountyPontotoc CountyPottawatomie CountyPushmataha CountyRoger Mills CountyRogers CountySeminole CountySequoyah CountyStephens CountyTexas CountyTillman CountyTulsa CountyWagoner CountyWashington CountyWashita CountyWoods CountyWoodward CountyGoogle Tulsa County data center campus (Project Clydesdale) · Under constructionTierPoint Tulsa - Archer · OperatingTierPoint Tulsa - State Farm · OperatingTulsaConnect East (DC-3) · OperatingTulsaConnect Downtown (DC-5) · Operating
Projects in Tulsa County
Google Tulsa County data center campus (Project Clydesdale)Beale Infrastructure; Google—Under constructionAug. 20, 202650 MW+
TierPoint Tulsa - ArcherTierPoint—OperatingOct. 2026Under 50 MW
TierPoint Tulsa - State FarmTierPoint; Compass Datacenters—OperatingFeb. 27, 2018Under 50 MW
TulsaConnect Downtown (DC-5)TulsaConnect—OperatingOct. 16, 2026Under 50 MW
TulsaConnect East (DC-3)TulsaConnect—OperatingOct. 16, 2026Under 50 MW

Moratoriums and bans

  1. March 25, 2026 Tulsa: Moratorium. The council voted unanimously to pause new data center construction for nine months, cut from a proposed one year. Both phases of Project Anthem in east Tulsa were exempted, and Project Clydesdale, already under construction, was not affected. (Tulsa Flyer via KOSU, March 27, 2026)
  2. June 15, 2026 Broken Arrow: Moratorium. The council approved a six-month pause, ending Dec. 31 and extendable, on land use applications for data centers. The city's zoning code does not list data centers as a use. Days earlier, the city said a letter of intent to sell land in east Broken Arrow had expired. (KJRH 2 News Oklahoma, June 15, 2026; City of Broken Arrow, June 12, 2026; City of Broken Arrow, June 10, 2026)

Updates, newest first

  1. Oct. 16, 2026 TulsaConnect East (DC-3) · Listed as operating in News 9's roundup, which notes it sits 18 feet underground. (News 9 / News On 6, Oct. 16, 2026; TulsaConnect, undated)
  2. Oct. 16, 2026 TulsaConnect Downtown (DC-5) · Listed as operating by the operator and in News 9's roundup. (TulsaConnect, undated; News 9 / News On 6, Oct. 16, 2026)
  3. Oct. 2026 TierPoint Tulsa - Archer · TierPoint lists the Archer site with over 36,000 sq ft, over 4,000 sq ft of raised floor and two 1 MW generators. (TierPoint, Oct. 23, 2026)
  4. Aug. 19, 2026 Google Tulsa County data center campus (Project Clydesdale) · Google said it will operate the campus, with PSO serving it through a new on-site substation funded by Beale. (Tulsa Regional Chamber, Aug. 19, 2026; News 9, Aug. 20, 2026; DatacenterDynamics, Aug. 19, 2026; Google, 2026)
  5. June 15, 2026 Broken Arrow: Moratorium · The council approved a six-month pause, ending Dec. 31 and extendable, on land use applications for data centers. The city's zoning code does not list data centers as a use. Days earlier, the city said a letter of intent to sell land in east Broken Arrow had expired. (KJRH 2 News Oklahoma, June 15, 2026; City of Broken Arrow, June 12, 2026; City of Broken Arrow, June 10, 2026)
  6. March 25, 2026 Tulsa: Moratorium · The council voted unanimously to pause new data center construction for nine months, cut from a proposed one year. Both phases of Project Anthem in east Tulsa were exempted, and Project Clydesdale, already under construction, was not affected. (Tulsa Flyer via KOSU, March 27, 2026)
  7. Oct. 30, 2025 Google Tulsa County data center campus (Project Clydesdale) · Beale broke ground on the campus, planned as one to four phases of about 200,000 square feet. (DatacenterDynamics, Nov. 3, 2025; Tulsa Regional Chamber, Aug. 19, 2026)
  8. Sept. 29, 2025 Google Tulsa County data center campus (Project Clydesdale) · Commissioners unanimously approved Project Clydesdale's plan and incentive districts. (Public Radio Tulsa, Sept. 29, 2025)
  9. July 16, 2025 Google Tulsa County data center campus (Project Clydesdale) · Tulsa County commissioners voted 3-0 after a three-hour hearing to rezone the land from agricultural to light industrial; residents raised water, wildlife and grid concerns. (Public Radio Tulsa, July 17, 2025)
  10. Feb. 27, 2018 TierPoint Tulsa - State Farm · DCD reported TierPoint had completed the State Farm Blvd. building, built with Compass, and had begun installing clients. (Data Center Dynamics, Feb. 27, 2018)
  11. May 31, 2017 TierPoint Tulsa - Archer · DCD described TierPoint's existing 37,000 sq ft Tulsa data center in the Brady District. (Data Center Dynamics, May 31, 2017)
  12. May 31, 2017 TierPoint Tulsa - State Farm · TierPoint said it would build a $20 million, 30,000 sq ft data center with 16,000 sq ft of raised floor near Tulsa with Compass Datacenters. (Data Center Dynamics, May 31, 2017)
  13. May 30, 2017 TierPoint Tulsa - State Farm · TierPoint announced a second Tulsa-area data center with Compass Datacenters: a $20 million first phase of about 30,000 sq ft with 16,000 sq ft of raised floor, in a building planned to reach about 60,000 sq ft. (TierPoint, May 30, 2017)

Statewide

Sales tax (Tax Commission rules): machinery and equipment such as computers and servers bought by a computer and data processing business (SIC 7374) are exempt if at least 80% of its yearly gross revenue comes from out-of-state buyers (OAC 710:65-13-54); electricity is not covered. A separate exemption for web search portals (68 O.S. §1357(38), NAICS 519130, same 80% test; OAC 710:65-13-650) does cover electric power, according to the Commerce Department. (Oklahoma Department of Commerce, undated; Oklahoma Administrative Code (via Cornell LII), undated; Oklahoma Administrative Code (via Justia), undated) Property tax: the five-year manufacturing ad valorem exemption (68 O.S. §2902(C)(5)) covers NAICS 518210 data processing sites that add $7 million in capital improvements or $250,000 in annual payroll. The general provision applies to assets placed in service by the end of 2021; sites that already had an exemption in the five years before Nov. 1, 2021 can claim personal property placed in service through 2036. A November 2024 review for the state Incentive Evaluation Commission found Google took 97.6% of data processing exemptions in FY2016–FY2020, and state reimbursements for computer data processing reached $46.6 million in 2022. (Oklahoma Incentive Evaluation Commission (PFM Group Consulting), Nov. 14, 2024; Oklahoma Department of Commerce, undated) HB 2992 (2026), the Data Center Customer Ratepayer Protection Act (17 O.S. §§900-906), was approved by the governor May 11, 2026 and took effect July 1. It covers new data centers, crypto mines and AI computing sites that contract to add 75 MW or more after July 1, 2026. Electric suppliers must give them separate terms so other customers don't carry their costs. Buyers of land outside a municipality or industrial park must notify the Corporation Commission, the county commissioners and abutting owners within 60 days, by certified mail (§906). The OCC posted an attestation form for this. (Oklahoma Corporation Commission, July 29, 2026; Oklahoma Corporation Commission, 2026; Oklahoma House of Representatives, May 13, 2026; KGOU / StateImpact Oklahoma, May 13, 2026) SB 259 (2026), the Groundwater Modernization Act, was approved May 20, 2026 and takes effect Nov. 1, 2026. Groundwater permit holders must file yearly use reports with the Water Resources Board. A data center can get a groundwater permit only if it uses closed-loop, immersion or other low-consumption cooling, not open evaporative systems. The rule doesn't reach centers that buy water from a utility or water district, a gap the bill's House author said he plans to address with a new bill next year. (Oklahoma House of Representatives, Aug. 6, 2026; KGOU / OPMX, April 13, 2026; Investigate Midwest, July 14, 2026) SB 480 (2025) allows private behind-the-meter power generation, which The Frontier described as letting data centers make their own electricity without being regulated as utilities. HB 2992 excludes entities that build behind-the-meter generation from its large-load rules. The Frontier reported Aligned would be among the first to use this law, near Amber. (Oklahoma Department of Commerce, June 6, 2025; Oklahoma Corporation Commission, July 29, 2026; The Frontier, Sept. 23, 2026) Bills that failed in 2026: SB 1488 (Sen. Sacchieri), introduced in January 2026, would have stopped new data center construction until Nov. 1, 2029 while the Corporation Commission studied water, rates, property values and siting; it never got a hearing. HB 3392 (OCC study of large users), HB 3394 (data center directory) and HB 3397 (separate rate class) were also filed; The Frontier reported that only two data center bills, HB 2992 and SB 259, passed and at least five others failed. Oklahoma has no statewide moratorium. (Oklahoma Legislature, Jan. 9, 2026; DCD, Jan. 26, 2026; HPPR / StateImpact Oklahoma, Feb. 16, 2026; The Frontier, Sept. 23, 2026) OCC Cause No. PUD2025-000075 (Public Service Company of Oklahoma rate case, filed January 2026): PSO proposed new terms under its Large Power and Light tariff so new large customers pay their full grid connection costs. The large-load tariff was split onto its own testimony track in June 2026. An administrative law judge's report, filed Aug. 21, 2026, recommended a new rate class for customers adding more than 75 MW, which PSO did not join. Commissioners had not issued a final order as of September 2026. Interim rates, subject to refund, took effect July 1, 2026. (Edison Electric Institute, Oct. 2026; Oklahoma Energy Today, April 27, 2026; Citizen Portal, June 29, 2026; Tulsa Flyer, Aug. 24, 2026; KOKH Fox 25, Sept. 8, 2026) OCC Cause No. PUD2026-000046 (OG&E Extra Large Power and Light tariff, filed June 17, 2026): it would apply to new loads of 75 MW or more, or to existing customers adding 75 MW or growing past 125 MW. Terms include 15-year contracts with a ramp of up to five years and minimum bills. A monthly charge would fund $25-30 million a year in credits to residential customers. A July 2026 order set Nov. 3, 2026 for a decision, but on Oct. 21 commissioners voted 3-0 to extend the case and send it back to an administrative law judge, citing legal and jurisdictional issues raised in testimony. A hearing on the merits is set for Jan. 12, 2027, so a decision is now expected in 2027. (OG&E, June 18, 2026; KGOU / StateImpact Oklahoma, June 18, 2026; Oklahoma Energy Today, July 10, 2026; Oklahoma Energy Today, Oct. 22, 2026; Edison Electric Institute, Oct. 2026) Siting: no state data center siting law exists beyond HB 2992's land-purchase notice. Grady County's legal counsel advised in September 2026 that only municipalities, not counties, can adopt a data center moratorium. Lawton set its threshold at 2 MW, which local reporting called the most restrictive level state law allows. (KGOU / OPMX, Sept. 30, 2026; The Frontier, Sept. 23, 2026; KSWO, Feb. 25, 2026) Oklahoma data centers →