Data center campus · Former Highway Auto Parts junkyard, Eynon Jermyn Road, Archbald Borough, Lackawanna County, Pennsylvania

Project Boson

Proposed as of April 2, 2026

A data center on a former auto junkyard along Eynon Jermyn Road in Archbald, filed before the borough's data center overlay and now in state stormwater permit review. Also known as: Archbald Energy & Data Center LLC, Archbald Data & Energy Center.

Cite← Pennsylvania data centers
Adams CountyAllegheny CountyArmstrong CountyBeaver CountyBedford CountyBerks CountyBlair CountyBradford CountyBucks CountyButler CountyCambria CountyCameron CountyCarbon CountyCentre CountyChester CountyClarion CountyClearfield CountyClinton CountyColumbia CountyCrawford CountyCumberland CountyDauphin CountyDelaware CountyElk CountyErie CountyFayette CountyForest CountyFranklin CountyFulton CountyGreene CountyHuntingdon CountyIndiana CountyJefferson CountyJuniata CountyLackawanna CountyLancaster CountyLawrence CountyLebanon CountyLehigh CountyLuzerne CountyLycoming CountyMcKean CountyMercer CountyMifflin CountyMonroe CountyMontgomery CountyMontour CountyNorthampton CountyNorthumberland CountyPerry CountyPhiladelphia CountyPike CountyPotter CountySchuylkill CountySnyder CountySomerset CountySullivan CountySusquehanna CountyTioga CountyUnion CountyVenango CountyWarren CountyWashington CountyWayne CountyWestmoreland CountyWyoming CountyYork CountyProject Boson · Proposed
PowerNot statedNot reported in the records found
Floor area620,000sq ft

Who is behind it

ProjectProject BosonAlso: Archbald Energy & Data Center LLC, Archbald Data & Energy Center
Developer and teamJim Marzolino (through Archbald Energy & Data Center LLC)
End userNot found in the recordsNot yet named in any record or credited report we have found.

The record, newest first

  1. DEP's tracker lists the project as under review, with one permit pending, one returned and four not yet submitted. (Pennsylvania Department of Environmental Protection, Oct. 31, 2026; Pennsylvania Department of Environmental Protection, Oct. 31, 2026)

  2. An individual Chapter 102 NPDES stormwater permit application (PAD350071) was submitted to DEP; it is listed as pending. (Pennsylvania Department of Environmental Protection, Oct. 31, 2026; Pennsylvania Department of Environmental Protection, Oct. 31, 2026)

  3. 28/22 News described Project Boson as a single building of about 620,000 sq ft on the former junkyard site; because it was filed before the borough's data center overlay, it can bypass the conditional use process. (WBRE/WYOU 28/22 News, March 28, 2026)

  4. WILK reported that the same developer, Jim Marzolino, applied for a zoning permit for a roughly 491,800 sq ft power plant on the west side of Eynon Jermyn Road, across from the junkyard and under 1,000 feet from Staback Park. (WILK News (Audacy), March 23, 2026)

  5. DEP's tracker shows an Act 537 sewage planning submission for the project, later returned. (Pennsylvania Department of Environmental Protection, Oct. 31, 2026; Pennsylvania Department of Environmental Protection, Oct. 31, 2026)

Conflicts and open questions

  • The power plant application is a separate filing by the same developer; whether it would serve Project Boson is not stated in the sources.

The full record

Status note
Filed under Archbald's earlier zoning, so it skipped a conditional use hearing; DEP lists an individual stormwater (NPDES) permit application as pending.
Power note
No power figure published in the sources reviewed; under 100 acres, so included as a smaller proposed campus.
Evidence
Primary public records
Size class
Under 50 MW (outside main scope; kept for completeness)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.