Data center campus · 100 South Commons, Suite 126 (Nova Place), North Side, Pittsburgh, Allegheny County, Pennsylvania

DataBank PIT1, Downtown Pittsburgh (Nova Place)

Operating as of Oct. 31, 2026

DataBank's downtown Pittsburgh data center, PIT1, sits in the Nova Place complex on the North Side and has been expanded twice since 2018. Also known as: Downtown Pittsburgh Data Center: PIT1.

Cite← Pennsylvania data centers
Adams CountyAllegheny CountyArmstrong CountyBeaver CountyBedford CountyBerks CountyBlair CountyBradford CountyBucks CountyButler CountyCambria CountyCameron CountyCarbon CountyCentre CountyChester CountyClarion CountyClearfield CountyClinton CountyColumbia CountyCrawford CountyCumberland CountyDauphin CountyDelaware CountyElk CountyErie CountyFayette CountyForest CountyFranklin CountyFulton CountyGreene CountyHuntingdon CountyIndiana CountyJefferson CountyJuniata CountyLackawanna CountyLancaster CountyLawrence CountyLebanon CountyLehigh CountyLuzerne CountyLycoming CountyMcKean CountyMercer CountyMifflin CountyMonroe CountyMontgomery CountyMontour CountyNorthampton CountyNorthumberland CountyPerry CountyPhiladelphia CountyPike CountyPotter CountySchuylkill CountySnyder CountySomerset CountySullivan CountySusquehanna CountyTioga CountyUnion CountyVenango CountyWarren CountyWashington CountyWayne CountyWestmoreland CountyWyoming CountyYork CountyDataBank PIT1, Downtown Pittsburgh (Nova Place) · Operating · 1.9 MW
Power1.9MW reported · stated
Floor area30,760sq ft
IT load1.9MW

Who is behind it

ProjectDataBank PIT1, Downtown Pittsburgh (Nova Place)Also: Downtown Pittsburgh Data Center: PIT1
Developer and teamDataBank
End userNot found in the recordsNot yet named in any record or credited report we have found.

The record, newest first

  1. DataBank's Pittsburgh page lists PIT1 at 30,760 square feet of IT space and 1.9 MW of critical IT load. (DataBank, Oct. 31, 2026)

  2. DataBank said a 10,500-square-foot expansion was ready, giving PIT1 25,000 square feet of raised floor and 2 MW of critical power. (DataBank, July 17, 2019)

  3. DataBank announced it would add 10,000 square feet of raised floor next to the existing 10,000-square-foot space, plus 1.5 MW of redundant power, ready in the fourth quarter of 2018. (DataBank, May 23, 2018)

Conflicts and open questions

  • sqft is IT square footage as DataBank states it.

The full record

Status note
Listed by DataBank as an operating facility.
Power note
1.9 MW critical IT load per DataBank's Pittsburgh page; its 2019 release gave 2 MW total critical power.
Evidence
Primary public records
Size class
Under 50 MW (outside main scope; kept for completeness)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.