Misty Hollow Energy and Data Campus
A developer filed plans for a 1-million-square-foot data center with its own gas-fired power station on a 274-acre former farm in Forward Township, which has no zoning. Also known as: Misty Hollow data center.
Who is behind it
The record, newest first
Residents raised fears that the project would strain volunteer fire department resources. (Pittsburgh Post-Gazette (republished by Fire Engineering via TNS), Oct. 22, 2026)
The township planning commission voted to table the proposal; the township manager said the engineer had reported 16 deficiencies to resolve. (Butler Eagle, Oct. 9, 2026)
The planning commission presentation was postponed because too many people came; it was moved to Oct. 1 at a larger venue. (WPXI-TV, Sept. 24, 2026)
Butler Eagle reported the preliminary plan: a 1 million sq ft data center, a power station, an 80,000 sq ft wastewater plant and room for a 416,000 sq ft expansion, with final approvals sought early 2027. (Butler Eagle, Sept. 19, 2026)
Conflicts and open questions
- Forward Township has no zoning ordinance; supervisors were expected to vote in November 2026 on a subdivision and land development ordinance amendment (Butler Eagle, Sept.), and a former supervisor said new rules likely would not apply to this already-filed plan (Butler Eagle, Oct.).
- Coordinates are approximate (Forward Township); no parcel coordinates used.
- Not on DEP's data center permit tracker as of Oct. 31, 2026.
- Allen Sherwood is named in reporting as the project's developer/spokesman.
The full record
- Status note
- Preliminary land development plan filed; the township planning commission tabled it in early October 2026 with 16 engineering deficiencies outstanding.
- Power note
- On-site gas-fired power station planned on about 10 acres; no capacity published.
- Evidence
- News reports; primary records not yet obtained
- Size class
- 50 MW or more (tracker scope)