Data center campus · 2500 Liberty Drive, Allen Township, Northampton County, Pennsylvania

Prologis Lehigh Valley East 16 data center conversion (Allen Township)

Approved as of March 24, 2026

Allen Township supervisors unanimously approved Prologis' plan to convert a 1-million-square-foot warehouse built in 2023 into a data center, described as possibly the Lehigh Valley's first hyperscale site. Also known as: Unnamed Data Center (Verdantas / Prologis) (DEP tracker).

Cite← Pennsylvania data centers
Adams CountyAllegheny CountyArmstrong CountyBeaver CountyBedford CountyBerks CountyBlair CountyBradford CountyBucks CountyButler CountyCambria CountyCameron CountyCarbon CountyCentre CountyChester CountyClarion CountyClearfield CountyClinton CountyColumbia CountyCrawford CountyCumberland CountyDauphin CountyDelaware CountyElk CountyErie CountyFayette CountyForest CountyFranklin CountyFulton CountyGreene CountyHuntingdon CountyIndiana CountyJefferson CountyJuniata CountyLackawanna CountyLancaster CountyLawrence CountyLebanon CountyLehigh CountyLuzerne CountyLycoming CountyMcKean CountyMercer CountyMifflin CountyMonroe CountyMontgomery CountyMontour CountyNorthampton CountyNorthumberland CountyPerry CountyPhiladelphia CountyPike CountyPotter CountySchuylkill CountySnyder CountySomerset CountySullivan CountySusquehanna CountyTioga CountyUnion CountyVenango CountyWarren CountyWashington CountyWayne CountyWestmoreland CountyWyoming CountyYork CountyPrologis Lehigh Valley East 16 data center conversion (Allen Township) · Approved
PowerNot statedNot reported in the records found
Floor area1,000,000sq ft

Who is behind it

ProjectPrologis Lehigh Valley East 16 data center conversion (Allen Township)Also: Unnamed Data Center (Verdantas / Prologis) (DEP tracker)
Developer and teamPrologis
End userNot found in the recordsNot yet named in any record or credited report we have found.

The record, newest first

  1. The state Department of Environmental Protection's data center permit tracker lists the project as proposed, with no permit applications received. (Pennsylvania Department of Environmental Protection, Oct. 31, 2026; Pennsylvania Department of Environmental Protection, Oct. 31, 2026)

  2. The Lehigh Valley Planning Commission's planning committee recommended asking for more detail on water, power, cooling and emergency plans. (Lehigh Valley Public Media, April 22, 2026)

  3. Supervisors unanimously approved amended preliminary/final land development plans to convert the warehouse, with no added footprint. (WFMZ-TV 69 News, March 24, 2026)

Conflicts and open questions

  • MW and acreage not reported; kept as an approved large conversion that may fall under the 50 MW floor.
  • The Apr. 21 date is inferred from the Apr. 22 story ('Tuesday').
  • DEP lists Verdantas with Prologis; Verdantas's role is not stated in the sources read.

The full record

Evidence
Primary public records
Size class
Under 50 MW (outside main scope; kept for completeness)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.