Smithfield Gateway data center
A two-building data center sketch plan at Smithfield Gateway drew resident opposition as Smithfield Township wrote data center zoning rules.
Who is behind it
The record, newest first
DEP's tracker lists the project as proposed, with no permit applications received. (Pennsylvania Department of Environmental Protection, Oct. 31, 2026; Pennsylvania Department of Environmental Protection, Oct. 31, 2026)
Supervisors held a public hearing on a data center zoning ordinance; the Smithfield Gateway plan was the only data center proposal before the township. (FOX56, Aug. 12, 2026)
Developer Jim DePetris updated the planning commission on a sketch plan for two data center buildings, each with a footprint of about 125,000 sq ft, plus a substation; data centers are a conditional use in the site's Economic Development zone. (Pocono Record (via AOL), undated)
Conflicts and open questions
- The Pocono Record page showed no publication date; the February 2026 date is inferred from its reference to a Feb. 12 planning meeting and should be checked.
- Outcome of the August 2026 ordinance vote not found.
- Size not reported; it may fall under the 50 MW scope floor.
The full record
- Status note
- At sketch-plan stage; the township held a hearing on a new data center zoning ordinance in August 2026.
- Power note
- No power or acreage figure is public.
- Evidence
- Primary public records
- Size class
- Under 50 MW (outside main scope; kept for completeness)