Data center campus · Off Route 31 near I-70, east of the Renaissance Faire entrance, South Huntingdon Township, Westmoreland County, Pennsylvania

TriEnergy / Stanton Farm data center (South Huntingdon Township)

Proposed as of Oct. 13, 2026

TriEnergy has applied to build a data center in a 1-million-square-foot building on 178 acres of farmland near I-70 in South Huntingdon Township. Also known as: TriEnergy Inc. / Stanton Farm LLC.

Cite← Pennsylvania data centers
Adams CountyAllegheny CountyArmstrong CountyBeaver CountyBedford CountyBerks CountyBlair CountyBradford CountyBucks CountyButler CountyCambria CountyCameron CountyCarbon CountyCentre CountyChester CountyClarion CountyClearfield CountyClinton CountyColumbia CountyCrawford CountyCumberland CountyDauphin CountyDelaware CountyElk CountyErie CountyFayette CountyForest CountyFranklin CountyFulton CountyGreene CountyHuntingdon CountyIndiana CountyJefferson CountyJuniata CountyLackawanna CountyLancaster CountyLawrence CountyLebanon CountyLehigh CountyLuzerne CountyLycoming CountyMcKean CountyMercer CountyMifflin CountyMonroe CountyMontgomery CountyMontour CountyNorthampton CountyNorthumberland CountyPerry CountyPhiladelphia CountyPike CountyPotter CountySchuylkill CountySnyder CountySomerset CountySullivan CountySusquehanna CountyTioga CountyUnion CountyVenango CountyWarren CountyWashington CountyWayne CountyWestmoreland CountyWyoming CountyYork CountyTriEnergy / Stanton Farm data center (South Huntingdon Township) · Proposed
PowerNot statedNot reported in the records found
Floor area1,000,000sq ft
Site178acres

Who is behind it

ProjectTriEnergy / Stanton Farm data center (South Huntingdon Township)Also: TriEnergy Inc. / Stanton Farm LLC
Developer and teamTriEnergy Inc.
Sippel Development Co.
Stanton Farm LLC (landowner) (through Stanton Farm LLC)
End userNot found in the recordsNot yet named in any record or credited report we have found.

The record, newest first

  1. Marcellus Drilling News reported the plan at 1.1 million sq ft, naming Sippel Development and TriEnergy as developers. (Marcellus Drilling News, Oct. 14, 2026)

  2. Supervisors adopted a data center ordinance amid strong resident opposition. (TribLive, Oct. 13, 2026)

  3. TriEnergy applied to the township for a land use permit for a $25 million data center. (TribLive, Oct. 13, 2026)

  4. Chapter 105 water obstruction and encroachment permit application (E6505225-014) submitted to DEP; DEP also lists an issued PAG-02 construction stormwater permit. (Pennsylvania Department of Environmental Protection, Oct. 31, 2026; Pennsylvania Department of Environmental Protection, Oct. 31, 2026)

  5. TriEnergy and landowner Stanton Farm signed a three-year agreement. (TribLive, Oct. 13, 2026)

Conflicts and open questions

  • Building size 1 million sq ft (TribLive) or 1.1 million (Marcellus Drilling News).
  • Tenaska plant capacity reported as 950 MW (TribLive) and 940 MW (MDN).
  • TribLive says the Westmoreland Conservation District approved a permit for a warehouse in January 2025 that does not mention a data center; DEP's tracker lists an issued PAG-02 (PAC650364), possibly the same permit (not confirmed).
  • Coordinates from DEP tracker.
  • TribLive names Douglas Sippel as a governor of Stanton Farm LLC; only Marcellus Drilling News names Sippel Development Co. as a developer.

The full record

Status note
Land use permit application filed in May 2026; township review waits on DEP sewage approval.
Power note
No load published; the 940-950 MW Tenaska Westmoreland gas plant is about a mile away, and the developer would not say whether it would buy power from it.
Evidence
Primary public records
Size class
50 MW or more (tracker scope)