Data centers · York County, South Carolina

York County

1 project on record · 2 moratorium or ban actions

← Statewide map
Abbeville CountyAiken CountyAllendale CountyAnderson CountyBamberg CountyBarnwell CountyBeaufort CountyBerkeley CountyCalhoun CountyCharleston CountyCherokee CountyChester CountyChesterfield CountyClarendon CountyColleton CountyDarlington CountyDillon CountyDorchester CountyEdgefield CountyFairfield CountyFlorence CountyGeorgetown CountyGreenville CountyGreenwood CountyHampton CountyHorry CountyJasper CountyKershaw CountyLancaster CountyLaurens CountyLee CountyLexington CountyMarion CountyMarlboro CountyMcCormick CountyNewberry CountyOconee CountyOrangeburg CountyPickens CountyRichland CountySaluda CountySpartanburg CountySumter CountyUnion CountyWilliamsburg CountyYork CountyQTS York County campus · Under construction
Projects in York County
QTS York County campusQTS Data Centers—Under constructionMay 14, 202650 MW+

Moratoriums and bans

  1. Feb. 6, 2026 York County: Zoning rules. Council voted 7-0 at a Feb. 6 special meeting on first reading of rules that would make data centers a special exception in Light Industrial and Industrial Development zones and a conditional use in Business and Technology districts, with 200-foot building and 300-foot ground-equipment setbacks from neighboring residential property, required acoustical studies and backup generators limited to emergencies and testing; invoking the pending ordinance doctrine applied the rules to new applications at once. A public hearing was set for March 16; final adoption is not confirmed, and in July council chose a broader study and a moratorium before rewriting the code. (WRHI, Feb. 11, 2026; WRHI, July 14, 2026)
  2. July 13, 2026 York County: Moratorium. Council voted 6-0 for a nine-month moratorium on site plans, special exceptions, conditional use permits and other approvals for new data centers (including cryptocurrency mining) in unincorporated areas, running to about April 2027; projects with civil site plan approval before it took effect are exempt within that approval. (WRHI, July 14, 2026)

Updates, newest first

  1. July 13, 2026 QTS York County campus · York County Council adopted a nine-month moratorium on new data center approvals in unincorporated areas; the county says projects with vested rights, such as QTS's approved site plans, are not affected. (York County, S.C., Oct. 24, 2026)
  2. July 13, 2026 York County: Moratorium · Council voted 6-0 for a nine-month moratorium on site plans, special exceptions, conditional use permits and other approvals for new data centers (including cryptocurrency mining) in unincorporated areas, running to about April 2027; projects with civil site plan approval before it took effect are exempt within that approval. (WRHI, July 14, 2026)
  3. May 12, 2026 QTS York County campus · At a second community meeting, QTS said phase one has four buildings and it is evaluating about nine buildings in total, beyond what is already approved. (The Post and Courier, May 14, 2026)
  4. Feb. 10, 2026 QTS York County campus · Neighbors described blasting, noise and lighting from construction; county council had just given first reading to new data center development standards. (WBTV, Feb. 10, 2026)
  5. Feb. 6, 2026 York County: Zoning rules · Council voted 7-0 at a Feb. 6 special meeting on first reading of rules that would make data centers a special exception in Light Industrial and Industrial Development zones and a conditional use in Business and Technology districts, with 200-foot building and 300-foot ground-equipment setbacks from neighboring residential property, required acoustical studies and backup generators limited to emergencies and testing; invoking the pending ordinance doctrine applied the rules to new applications at once. A public hearing was set for March 16; final adoption is not confirmed, and in July council chose a broader study and a moratorium before rewriting the code. (WRHI, Feb. 11, 2026; WRHI, July 14, 2026)
  6. Nov. 4, 2025 QTS York County campus · QTS held a public question-and-answer session in Clover; it said York Electric Cooperative would supply power and that QTS was paying for grid studies and upgrades. (The Post and Courier, Nov. 7, 2025)
  7. June 2025 QTS York County campus · County Council approved a zoning text amendment allowing taller buildings, which affected the QTS site. (York County, S.C., Oct. 24, 2026)
  8. Sept. 19, 2023 QTS York County campus · The governor's office announced a $1 billion QTS investment, its first in South Carolina, with a $200,000 state Set-Aside grant to the county for site preparation. (Office of the Governor of South Carolina, Sept. 19, 2023; Data Center Dynamics, Sept. 20, 2023)
  9. Sept. 18, 2023 QTS York County campus · York County Council gave final approval to a fee-in-lieu-of-tax agreement for QTS after three readings and a public hearing. (York County, S.C., Oct. 24, 2026)
  10. July 26, 2023 QTS York County campus · Two QTS-affiliated companies bought about 400 acres in three deals worth more than $11.2 million, including the county-owned tract marketed as Project Cobra. (Data Center Dynamics, July 26, 2023; York County, S.C., Oct. 24, 2026)

Statewide

The data center exemption in S.C. Code Section 12-36-2120, added by legislation in the 2011-2012 session, exempts qualifying data centers from sales and use tax on their electricity and on computer equipment and software, if the owner invests at least $50 million over five years, employs at least 25 full-time workers and pays wages of at least 150% of the county's per capita income; claims totaled about $828,000 in the fiscal year ending June 2025. (SC Daily Gazette, April 24, 2026; South Carolina General Assembly, Jan. 14, 2026) The South Carolina Energy Security Act (H. 3309, Act No. 41, signed May 12, 2025) cleared the Senate 35-11 on May 7, 2025, after the House dropped Senate amendments that would have ended data center tax incentives, required 15-year power contracts and made data centers report water use; its Section 32 (S.C. Code 58-41-50(E)) only encourages utilities to set operational and financial requirements for new loads over 50 MW, through form contracts, tariffs or service regulations, or credit policies. (South Carolina General Assembly, May 12, 2025; South Carolina General Assembly, Oct. 24, 2026; Southern Environmental Law Center, May 7, 2025; South Carolina Policy Council, Oct. 11, 2025) H. 5122 (Act No. 242, signed May 19, 2026) created a sales tax exemption and refund for internet and communications providers' equipment and electricity, but bars data centers with a contracted peak demand of 50 MW or more that become electric customers after Dec. 31, 2026, from using it; H. 4925 (2026), which would have extended the existing data center exemption to related persons of the taxpayer, never left House Ways and Means. (South Carolina General Assembly, May 19, 2026; South Carolina General Assembly, Jan. 14, 2026) Data center regulation bills died when the 2026 session ended May 14, 2026: S. 867 (Data Center Development Act: state permits, a new office at the Department of Environmental Services, PSC full-cost rules, water and noise standards) got a favorable Senate Agriculture and Natural Resources Committee report on April 28, 2026 but no floor vote; S. 784 (repeal data center tax incentives, 15-year contracts with collateral for loads of 100 MW or more) and S. 902 (Data Center Siting Act) never left Senate Judiciary. (South Carolina General Assembly, Jan. 29, 2026; South Carolina General Assembly, Jan. 13, 2026; South Carolina General Assembly, Feb. 10, 2026; WRHI, April 29, 2026; South Carolina Policy Council, Feb. 13, 2026; SC Daily Gazette, June 26, 2026; SC Daily Gazette, May 15, 2026) Two House joint resolutions for a statewide moratorium, H. 5286 (no final state or local approval of new data centers until Jan. 1, 2028; filed Feb. 26, 2026) and H. 5526 (no data center applications or permits for facilities of 5 MW or more until lawmakers set up an oversight and approval process; filed April 14, 2026), never left House Ways and Means. (South Carolina General Assembly, Feb. 26, 2026; South Carolina General Assembly, April 14, 2026; WMBF News, March 4, 2026) Santee Cooper's board unanimously adopted an experimental large-load rate (Schedule L-25-LL) effective April 25, 2025 and available through April 24, 2029; it is mandatory for data or computing facilities and other high-load-factor facilities over 50 MW, and requires contracts of at least 15 years, minimum bills and billing demand, collateral covering 15 years of minimum bills, and a ramp to full contracted load within three years. (SC Daily Gazette, April 25, 2025; Santee Cooper, April 25, 2025) Under settlements in their 2025 rate cases, Duke Energy Carolinas and Duke Energy Progress agreed to seek a generic docket on large new loads; on Duke's May 27, 2026 petition, the PSC opened Docket 2026-138-E to take comments on loads of 50 MW or more, covering minimum contract terms, billing demand, collateral, exit rules and cost treatment (Order No. 2026-362, June 17, 2026, set the procedural schedule). (Public Service Commission of South Carolina, July 6, 2026; Sierra Club, Oct. 30, 2025) South Carolina data centers →