Data center campus · LandBridge land near the Waha natural gas hub, Reeves County, Reeves County, Texas
Alpha Digital Campus (PowerBridge)
Proposed
as of July 22, 2026
A planned West Texas data center campus with up to 2 GW of on-site power on about 3,400 acres of LandBridge land in Reeves County, with first power targeted for late 2027.
Power2,000MW reported · stated
Site3,400acres
Who is behind it
ProjectAlpha Digital Campus (PowerBridge)
Developer and teamPowerBridge
LandBridge
Liberty Power Innovations (Liberty Energy)
LandBridge
Liberty Power Innovations (Liberty Energy)
End userNot found in the recordsNot yet named in any record or credited report we have found.
The record, newest first
Liberty Energy and PowerBridge announced a joint venture for the campus's power, with a first phase of more than 300 MW of generation and first power expected in the fourth quarter of 2027. (Liberty Energy, July 22, 2026)
LandBridge gave PowerBridge an option to lease up to about 3,400 acres in Reeves County for a powered data center campus with up to 2 GW of co-located generation; first power was targeted for 2027 and large-scale generation for 2028. (LandBridge, April 2, 2026)
Conflicts and open questions
- Coordinates are a county-level approximation near the Waha hub; no address or parcel has been published.
- The releases do not name the fuel; the location next to the Waha gas hub suggests natural gas, but that is not stated.
- The joint venture is still subject to further commercial agreements and regulatory approvals.
- ERCOT is inferred from PowerBridge's generation interconnection request (an ERCOT process); neither release names ERCOT.
The full record
- Power note
- 2 GW is the planned co-located generation; the first phase is expected to include more than 300 MW of generation.
- Evidence
- Primary public records
- Size class
- 50 MW or more (tracker scope)