Amazon Ezell Drive Campus (DeSoto)
Amazon Data Services registered plans for a data center building of about 30,000 sq ft, with cable-entry buildings and a pumphouse, on a vacant nine-acre DeSoto tract it bought in 2022.
Who is behind it
The record, newest first
Amazon Data Services registered the Ezell Drive Campus with TDLR: a 29,840 sq ft data center building with MEP infrastructure, cable-entry buildings and a pumphouse, estimated at $6 million, scheduled April 2023 to December 2024. (Texas Department of Licensing and Regulation, Sept. 13, 2022)
The Dallas Morning News reported that county records showed Amazon Data Services had bought a vacant tract of more than 9 acres in DeSoto, off Hampton Road south of I-20. (The Dallas Morning News, Jan. 7, 2022)
DCD reported the roughly 30,000 sq ft Ezell Drive Campus filing, a $6 million plan on a nine-acre tract bought at the start of the year, with completion targeted for 2024. (DatacenterDynamics, undated)
Conflicts and open questions
- Under 50 MW (inferred from size; no power figure published). Kept as a small facility per scope rules.
- TDLR lists an erroneous ZIP code for the address.
- Acreage and 2022 purchase come from DMN and DCD; neither page shows its date or title in fetched text (DMN date from URL).
The full record
- Status note
- TDLR registration (plan review complete) scheduled construction from April 2023 to December 2024; no public record found confirming construction, completion or operation.
- Power note
- Not reported; small single building, likely under 50 MW.
- Evidence
- Primary public records
- Size class
- Under 50 MW (outside main scope; kept for completeness)