Project LufKin (Amp Z)
A gigawatt-scale AI campus planned on a closed paper mill outside Lufkin that has drawn resident opposition and led Angelina County to ask the state for regulatory authority. Also known as: Champion Data Center Holdings.
Who is behind it
The record, newest first
Commissioners unanimously asked the Legislature for authority to set buffers, noise, light and water standards for large facilities like data centers. (KLTV, July 14, 2026)
Commissioners heard public comment against the project; the judge said the county cannot impose a moratorium and its leverage is limited to an abatement or road-use agreement. (The Texas Tribune, June 9, 2026; FOX 4 (FOX Local), June 10, 2026)
County Judge Keith Wright announced negotiations on a $1.5 billion Amp Z data center at the former paper mill site. (KLTV, Feb. 6, 2026)
Property records reported by the Lufkin Daily News showed Amp Z's Champion Data Center Holdings had rights to buy about 1,041 acres, expandable toward 4,000. (DatacenterDynamics, Feb. 2026)
Conflicts and open questions
- The developer's 2.1 GW campus figure includes a 1 GW on-site generation target; mw lists the 1.1 GW grid-connected figure.
- Investment figures differ: $1.5 billion (county judge) vs. $1 billion (city fact sheet).
- A proposed county tax abatement exists but no approval was found.
The full record
- Power note
- Grid-connected ramp reported: 55 MW now, 175 MW in 2026, 1.1 GW by 2028. The 2.1 GW campus total includes 1 GW of planned on-site self-generation by 2029, kept out of mw.
- Evidence
- News reports; primary records not yet obtained
- Size class
- 50 MW or more (tracker scope)