Data center campus · Off Westinghouse Road, Georgetown, Williamson County, Texas
Blueprint Data Centers Georgetown
Approved
as of Sept. 2024
A planned data center of up to 25 MW and about 45,000 square feet on about 10 acres off Westinghouse Road in Georgetown, tied to a larger Blueprint site in Taylor. Also known as: Georgetown DC.
Power25MW reported · stated
Floor area45,000sq ft
Site10acres
Who is behind it
ProjectBlueprint Data Centers GeorgetownAlso: Georgetown DC
Developer and teamBlueprint Data Centers
End userNot found in the recordsNot yet named in any record or credited report we have found.
The record, newest first
Blueprint committed about $160 million to the site, with a first phase expected to open in late 2026 and full completion in early 2027. (Hello Georgetown, Oct. 10, 2025)
Reporting says the Georgetown City Council approved zoning and incentives for the project (month only). (Hello Georgetown, Oct. 10, 2025)
Conflicts and open questions
- Under 50 MW.
- Only one dated source was opened; the council approval was not checked against city minutes.
- The September 2024 approval date is month-only in the reporting.
The full record
- Status note
- The city approved zoning and incentives in September 2024; the developer said in October 2025 it was preparing to break ground.
- Evidence
- News reports; primary records not yet obtained
- Size class
- Under 50 MW (outside main scope; kept for completeness)