Data center campus · Cotulla, La Salle County, Texas

Cipher Reveille site (Cotulla)

Proposed as of Feb. 24, 2026

Cipher owns a Cotulla data center site with ERCOT approval for up to 70 MW and expects to energize it in 2027. Also known as: Reveille.

Cite← Texas data centers
Anderson CountyAndrews CountyAngelina CountyAransas CountyArcher CountyArmstrong CountyAtascosa CountyAustin CountyBailey CountyBandera CountyBastrop CountyBaylor CountyBee CountyBell CountyBexar CountyBlanco CountyBorden CountyBosque CountyBowie CountyBrazoria CountyBrazos CountyBrewster CountyBriscoe CountyBrooks CountyBrown CountyBurleson CountyBurnet CountyCaldwell CountyCalhoun CountyCallahan CountyCameron CountyCamp CountyCarson CountyCass CountyCastro CountyChambers CountyCherokee CountyChildress CountyClay CountyCochran CountyCoke CountyColeman CountyCollin CountyCollingsworth CountyColorado CountyComal CountyComanche CountyConcho CountyCooke CountyCoryell CountyCottle CountyCrane CountyCrockett CountyCrosby CountyCulberson CountyDallam CountyDallas CountyDawson CountyDeaf Smith CountyDelta CountyDenton CountyDeWitt CountyDickens CountyDimmit CountyDonley CountyDuval CountyEastland CountyEctor CountyEdwards CountyEl Paso CountyEllis CountyErath CountyFalls CountyFannin CountyFayette CountyFisher CountyFloyd CountyFoard CountyFort Bend CountyFranklin CountyFreestone CountyFrio CountyGaines CountyGalveston CountyGarza CountyGillespie CountyGlasscock CountyGoliad CountyGonzales CountyGray CountyGrayson CountyGregg CountyGrimes CountyGuadalupe CountyHale CountyHall CountyHamilton CountyHansford CountyHardeman CountyHardin CountyHarris CountyHarrison CountyHartley CountyHaskell CountyHays CountyHemphill CountyHenderson CountyHidalgo CountyHill CountyHockley CountyHood CountyHopkins CountyHouston CountyHoward CountyHudspeth CountyHunt CountyHutchinson CountyIrion CountyJack CountyJackson CountyJasper CountyJeff Davis CountyJefferson CountyJim Hogg CountyJim Wells CountyJohnson CountyJones CountyKarnes CountyKaufman CountyKendall CountyKenedy CountyKent CountyKerr CountyKimble CountyKing CountyKinney CountyKleberg CountyKnox CountyLa Salle CountyLamar CountyLamb CountyLampasas CountyLavaca CountyLee CountyLeon CountyLiberty CountyLimestone CountyLipscomb CountyLive Oak CountyLlano CountyLoving CountyLubbock CountyLynn CountyMadison CountyMarion CountyMartin CountyMason CountyMatagorda CountyMaverick CountyMcCulloch CountyMcLennan CountyMcMullen CountyMedina CountyMenard CountyMidland CountyMilam CountyMills CountyMitchell CountyMontague CountyMontgomery CountyMoore CountyMorris CountyMotley CountyNacogdoches CountyNavarro CountyNewton CountyNolan CountyNueces CountyOchiltree CountyOldham CountyOrange CountyPalo Pinto CountyPanola CountyParker CountyParmer CountyPecos CountyPolk CountyPotter CountyPresidio CountyRains CountyRandall CountyReagan CountyReal CountyRed River CountyReeves CountyRefugio CountyRoberts CountyRobertson CountyRockwall CountyRunnels CountyRusk CountySabine CountySan Augustine CountySan Jacinto CountySan Patricio CountySan Saba CountySchleicher CountyScurry CountyShackelford CountyShelby CountySherman CountySmith CountySomervell CountyStarr CountyStephens CountySterling CountyStonewall CountySutton CountySwisher CountyTarrant CountyTaylor CountyTerrell CountyTerry CountyThrockmorton CountyTitus CountyTom Green CountyTravis CountyTrinity CountyTyler CountyUpshur CountyUpton CountyUvalde CountyVal Verde CountyVan Zandt CountyVictoria CountyWalker CountyWaller CountyWard CountyWashington CountyWebb CountyWharton CountyWheeler CountyWichita CountyWilbarger CountyWillacy CountyWilliamson CountyWilson CountyWinkler CountyWise CountyWood CountyYoakum CountyYoung CountyZapata CountyZavala CountyCipher Reveille site (Cotulla) · Proposed · 70 MW
Power70MW reported · record

Who is behind it

ProjectCipher Reveille site (Cotulla)Also: Reveille
Developer and teamCipher Digital (formerly Cipher Mining)
End userNot found in the recordsNot yet named in any record or credited report we have found.

The record, newest first

  1. Cipher's FY2025 10-K lists Reveille in Cotulla in its pipeline with up to 70 MW of ERCOT interconnection approval and energization expected in 2027. (U.S. Securities and Exchange Commission (Cipher Digital Inc.), Feb. 24, 2026)

  2. Cipher's Q3 2024 update said it closed on the 70 MW Reveille site and that it could expand to 200 MW. (U.S. Securities and Exchange Commission (Cipher Mining Inc.), Oct. 31, 2024)

  3. The Energy Mag reported Cipher agreed to buy a Cotulla site with at least 70 MW for $2.5 million. (The Energy Mag, June 4, 2024)

Conflicts and open questions

  • Over 50 MW threshold (70 MW).
  • Coordinates approximate (town of Cotulla); exact parcel not public.
  • Originally bought as a bitcoin mining site; filings now group it with Cipher's data center pipeline without naming a final use.

The full record

Status note
Site owned; energization expected in 2027.
Power note
ERCOT interconnection approval of up to 70 MW per the 10-K; Cipher said in 2024 it could grow to 200 MW.