Core Scientific Hunt County campus
Core Scientific closed a roughly $233 million purchase of land and power in Hunt County for a site it says can support about 430 MW of gross capacity under an approved ERCOT interconnection ramp schedule.
Who is behind it
The record, newest first
The company reported closing the Hunt County land and power acquisition for about $233 million. (Core Scientific (SEC Form 8-K, Exhibit 99.1), May 6, 2026)
A company representative presented the plan, its infrastructure needs and expected economic impact to the Hunt County Commissioners Court. (Herald-Banner (via Ground News), March 25, 2026)
Core Scientific disclosed an agreement to expand into Hunt County, at a site expected to support about 430 MW of gross capacity with an approved ERCOT interconnection ramp schedule. (Core Scientific, March 2, 2026)
Conflicts and open questions
- Coordinates are approximate; the company releases do not give the site's location within Hunt County.
- Company releases do not say what workloads the Hunt County site will serve; Core Scientific describes itself as a high-density colocation provider.