Data center campus · near the Port of Victoria, Calhoun County, Calhoun County, Texas

Crusoe AI campus near Port of Victoria

Proposed as of Oct. 30, 2025

Crusoe plans a 1,600-acre AI data center campus near the Port of Victoria to be powered by a Blue Energy gas plant that would later convert to nuclear, up to 1.5 GW of reactor capacity. Also known as: Crusoe Victoria, Blue Energy / Crusoe gas-to-nuclear campus.

Cite← Texas data centers
Anderson CountyAndrews CountyAngelina CountyAransas CountyArcher CountyArmstrong CountyAtascosa CountyAustin CountyBailey CountyBandera CountyBastrop CountyBaylor CountyBee CountyBell CountyBexar CountyBlanco CountyBorden CountyBosque CountyBowie CountyBrazoria CountyBrazos CountyBrewster CountyBriscoe CountyBrooks CountyBrown CountyBurleson CountyBurnet CountyCaldwell CountyCalhoun CountyCallahan CountyCameron CountyCamp CountyCarson CountyCass CountyCastro CountyChambers CountyCherokee CountyChildress CountyClay CountyCochran CountyCoke CountyColeman CountyCollin CountyCollingsworth CountyColorado CountyComal CountyComanche CountyConcho CountyCooke CountyCoryell CountyCottle CountyCrane CountyCrockett CountyCrosby CountyCulberson CountyDallam CountyDallas CountyDawson CountyDeaf Smith CountyDelta CountyDenton CountyDeWitt CountyDickens CountyDimmit CountyDonley CountyDuval CountyEastland CountyEctor CountyEdwards CountyEl Paso CountyEllis CountyErath CountyFalls CountyFannin CountyFayette CountyFisher CountyFloyd CountyFoard CountyFort Bend CountyFranklin CountyFreestone CountyFrio CountyGaines CountyGalveston CountyGarza CountyGillespie CountyGlasscock CountyGoliad CountyGonzales CountyGray CountyGrayson CountyGregg CountyGrimes CountyGuadalupe CountyHale CountyHall CountyHamilton CountyHansford CountyHardeman CountyHardin CountyHarris CountyHarrison CountyHartley CountyHaskell CountyHays CountyHemphill CountyHenderson CountyHidalgo CountyHill CountyHockley CountyHood CountyHopkins CountyHouston CountyHoward CountyHudspeth CountyHunt CountyHutchinson CountyIrion CountyJack CountyJackson CountyJasper CountyJeff Davis CountyJefferson CountyJim Hogg CountyJim Wells CountyJohnson CountyJones CountyKarnes CountyKaufman CountyKendall CountyKenedy CountyKent CountyKerr CountyKimble CountyKing CountyKinney CountyKleberg CountyKnox CountyLa Salle CountyLamar CountyLamb CountyLampasas CountyLavaca CountyLee CountyLeon CountyLiberty CountyLimestone CountyLipscomb CountyLive Oak CountyLlano CountyLoving CountyLubbock CountyLynn CountyMadison CountyMarion CountyMartin CountyMason CountyMatagorda CountyMaverick CountyMcCulloch CountyMcLennan CountyMcMullen CountyMedina CountyMenard CountyMidland CountyMilam CountyMills CountyMitchell CountyMontague CountyMontgomery CountyMoore CountyMorris CountyMotley CountyNacogdoches CountyNavarro CountyNewton CountyNolan CountyNueces CountyOchiltree CountyOldham CountyOrange CountyPalo Pinto CountyPanola CountyParker CountyParmer CountyPecos CountyPolk CountyPotter CountyPresidio CountyRains CountyRandall CountyReagan CountyReal CountyRed River CountyReeves CountyRefugio CountyRoberts CountyRobertson CountyRockwall CountyRunnels CountyRusk CountySabine CountySan Augustine CountySan Jacinto CountySan Patricio CountySan Saba CountySchleicher CountyScurry CountyShackelford CountyShelby CountySherman CountySmith CountySomervell CountyStarr CountyStephens CountySterling CountyStonewall CountySutton CountySwisher CountyTarrant CountyTaylor CountyTerrell CountyTerry CountyThrockmorton CountyTitus CountyTom Green CountyTravis CountyTrinity CountyTyler CountyUpshur CountyUpton CountyUvalde CountyVal Verde CountyVan Zandt CountyVictoria CountyWalker CountyWaller CountyWard CountyWashington CountyWebb CountyWharton CountyWheeler CountyWichita CountyWilbarger CountyWillacy CountyWilliamson CountyWilson CountyWinkler CountyWise CountyWood CountyYoakum CountyYoung CountyZapata CountyZavala CountyCrusoe AI campus near Port of Victoria · Proposed
PowerNot statedNot reported in the records found
Site1,600acres

Who is behind it

ProjectCrusoe AI campus near Port of VictoriaAlso: Crusoe Victoria, Blue Energy / Crusoe gas-to-nuclear campus
Developer and teamCrusoe
End userNot found in the recordsNot yet named in any record or credited report we have found.

The record, newest first

  1. Blue Energy signed with GE Vernova Hitachi to advance design and licensing; NEI reported phases of about 1 GW of gas turbines (2030) and up to 1.5 GWe of BWRX-300 reactors (2032), with a final investment decision expected in 2027. (Nuclear Engineering International, Aug. 17, 2026)

  2. NucNet reported Blue Energy could deploy up to 1.5 GW of reactor capacity to serve the Crusoe site. (NucNet, Nov. 3, 2025)

  3. Crusoe and Blue Energy announced a partnership for a 1,600-acre Crusoe AI campus near the Port of Victoria, powered first by natural gas as early as 2028 and by nuclear by 2031; Crusoe later corrected the county to Calhoun. (Crusoe, Oct. 30, 2025)

Conflicts and open questions

  • Data center MW not stated; the 1.5 GW and 2.5 GWe figures are power plant capacity, so mw left null.
  • No county, port or state permit records found yet; status from company announcements.
  • Exact site not published. Crusoe places it at the Port of Victoria but in Calhoun County; the port's turning basin itself sits in Victoria County, so the pin is set approximately inside Calhoun County and is not the site.

The full record

Evidence
News reports; primary records not yet obtained
Size class
50 MW or more (tracker scope)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.