Data center campus · Met Center business park, Metropolis Drive, southeast Austin, Travis County, Texas
CyrusOne Austin campus (AUS2, AUS3)
Operating
as of Oct. 29, 2026
CyrusOne's two-building colocation campus in Austin's Met Center business park (under 50 MW). Also known as: AUS2, AUS3.
PowerNot statedNot reported in the records found
Floor area242,000sq ft
IT load19MW
Who is behind it
ProjectCyrusOne Austin campus (AUS2, AUS3)Also: AUS2, AUS3
Developer and teamCyrusOne
End userNot found in the recordsNot yet named in any record or credited report we have found.
The record, newest first
CyrusOne lists AUS2 and AUS3 as one campus with 19 MW of IT capacity and 242,000 sq ft of technical space. (CyrusOne, Oct. 29, 2026)
CyrusOne registered a $50 million new two-story data center and office at 7201 Metropolis Drive with TDLR, with work scheduled from October 2018 to April 2020. (Texas Department of Licensing and Regulation, Oct. 12, 2017)
Conflicts and open questions
- Operator page does not give per-building addresses; the TDLR filing shows 7201 Metropolis Drive.
The full record
- Evidence
- Primary public records
- Size class
- Under 50 MW (outside main scope; kept for completeness)