Data center campus · West of Cedar Creek Lake between Trinidad and Tool, Henderson County, Texas

Diode Ventures Cedar Creek Lake data center

Withdrawn as of July 23, 2026

A data center proposed near Cedar Creek Lake, a major Fort Worth water source, that its developer dropped after a resident coalition organized against it; Gov. Greg Abbott said the project fell short of the state's standard.

Cite← Texas data centers
Anderson CountyAndrews CountyAngelina CountyAransas CountyArcher CountyArmstrong CountyAtascosa CountyAustin CountyBailey CountyBandera CountyBastrop CountyBaylor CountyBee CountyBell CountyBexar CountyBlanco CountyBorden CountyBosque CountyBowie CountyBrazoria CountyBrazos CountyBrewster CountyBriscoe CountyBrooks CountyBrown CountyBurleson CountyBurnet CountyCaldwell CountyCalhoun CountyCallahan CountyCameron CountyCamp CountyCarson CountyCass CountyCastro CountyChambers CountyCherokee CountyChildress CountyClay CountyCochran CountyCoke CountyColeman CountyCollin CountyCollingsworth CountyColorado CountyComal CountyComanche CountyConcho CountyCooke CountyCoryell CountyCottle CountyCrane CountyCrockett CountyCrosby CountyCulberson CountyDallam CountyDallas CountyDawson CountyDeaf Smith CountyDelta CountyDenton CountyDeWitt CountyDickens CountyDimmit CountyDonley CountyDuval CountyEastland CountyEctor CountyEdwards CountyEl Paso CountyEllis CountyErath CountyFalls CountyFannin CountyFayette CountyFisher CountyFloyd CountyFoard CountyFort Bend CountyFranklin CountyFreestone CountyFrio CountyGaines CountyGalveston CountyGarza CountyGillespie CountyGlasscock CountyGoliad CountyGonzales CountyGray CountyGrayson CountyGregg CountyGrimes CountyGuadalupe CountyHale CountyHall CountyHamilton CountyHansford CountyHardeman CountyHardin CountyHarris CountyHarrison CountyHartley CountyHaskell CountyHays CountyHemphill CountyHenderson CountyHidalgo CountyHill CountyHockley CountyHood CountyHopkins CountyHouston CountyHoward CountyHudspeth CountyHunt CountyHutchinson CountyIrion CountyJack CountyJackson CountyJasper CountyJeff Davis CountyJefferson CountyJim Hogg CountyJim Wells CountyJohnson CountyJones CountyKarnes CountyKaufman CountyKendall CountyKenedy CountyKent CountyKerr CountyKimble CountyKing CountyKinney CountyKleberg CountyKnox CountyLa Salle CountyLamar CountyLamb CountyLampasas CountyLavaca CountyLee CountyLeon CountyLiberty CountyLimestone CountyLipscomb CountyLive Oak CountyLlano CountyLoving CountyLubbock CountyLynn CountyMadison CountyMarion CountyMartin CountyMason CountyMatagorda CountyMaverick CountyMcCulloch CountyMcLennan CountyMcMullen CountyMedina CountyMenard CountyMidland CountyMilam CountyMills CountyMitchell CountyMontague CountyMontgomery CountyMoore CountyMorris CountyMotley CountyNacogdoches CountyNavarro CountyNewton CountyNolan CountyNueces CountyOchiltree CountyOldham CountyOrange CountyPalo Pinto CountyPanola CountyParker CountyParmer CountyPecos CountyPolk CountyPotter CountyPresidio CountyRains CountyRandall CountyReagan CountyReal CountyRed River CountyReeves CountyRefugio CountyRoberts CountyRobertson CountyRockwall CountyRunnels CountyRusk CountySabine CountySan Augustine CountySan Jacinto CountySan Patricio CountySan Saba CountySchleicher CountyScurry CountyShackelford CountyShelby CountySherman CountySmith CountySomervell CountyStarr CountyStephens CountySterling CountyStonewall CountySutton CountySwisher CountyTarrant CountyTaylor CountyTerrell CountyTerry CountyThrockmorton CountyTitus CountyTom Green CountyTravis CountyTrinity CountyTyler CountyUpshur CountyUpton CountyUvalde CountyVal Verde CountyVan Zandt CountyVictoria CountyWalker CountyWaller CountyWard CountyWashington CountyWebb CountyWharton CountyWheeler CountyWichita CountyWilbarger CountyWillacy CountyWilliamson CountyWilson CountyWinkler CountyWise CountyWood CountyYoakum CountyYoung CountyZapata CountyZavala CountyDiode Ventures Cedar Creek Lake data center · Withdrawn
PowerNot statedNot reported in the records found

Who is behind it

ProjectDiode Ventures Cedar Creek Lake data center
Developer and teamDiode Ventures
End userNot found in the recordsNot yet named in any record or credited report we have found.

The record, newest first

  1. Diode said it had wrapped up its work on the site and would not take it past preliminary planning; Gov. Abbott praised the withdrawal. (The Texas Tribune, July 23, 2026; ABC13 Houston (The Texas Tribune), July 25, 2026)

  2. Records reported by the Fort Worth Report showed Diode's water request would at least double the utility district's capacity; the Tarrant Regional Water District said Diode's application to it was incomplete. (KERA News (Fort Worth Report), July 2, 2026)

  3. Residents overflowed a West Cedar Creek Municipal Utility District meeting to oppose the project; the district advanced a temporary suspension of new high-intensity water service commitments running through April 1, 2027. (KETK, May 22, 2026; KERA News (Fort Worth Report), July 2, 2026)

Conflicts and open questions

  • Acreage and MW were never disclosed; included as a contested project because of its scale of water demand. Editors may judge whether it meets scope.
  • The exact withdrawal date is not given; the Tribune story ran July 23, 2026.
  • A county commissioner said landowners are still exploring other uses for the land.
  • Henderson County's May 2026 resolution is already in our moratorium list.

The full record

Evidence
News reports; primary records not yet obtained
Size class
Under 50 MW (outside main scope; kept for completeness)