Edged Dallas DFW01 campus (Irving)
Edged converted a vacant Irving warehouse into a waterless-cooled data center that opened in January 2025, and the city approved a second 24 MW building on the same street a year later. Also known as: Edged DFW Data Center, Edged Dallas.
Who is behind it
The record, newest first
REjournals reported Irving City Council unanimously approved a second Edged building with 24 MW of critical capacity, with groundbreaking expected in Q2 2026. (REjournals, Jan. 21, 2026)
KRLD reported the roughly 169,000 sq ft Irving data center had opened that week, with the company saying it uses no water for cooling. (KRLD (Audacy), Jan. 17, 2025)
DCD reported Edged had launched its 24 MW Irving data center at 505 North Wildwood Drive, cooled by a waterless system from sister company ThermalWorks. (DatacenterDynamics, undated)
Edged Dallas LLC registered a $35 million renovation with TDLR to turn a 162,543 sq ft warehouse at 505 N. Wildwood Drive into data halls. (Texas Department of Licensing and Regulation, Aug. 23, 2023)
Conflicts and open questions
- Building square footage differs: TDLR lists 162,543 sq ft; KRLD reported about 169,000 sq ft.
- The DCD launch article shows no publication date on the page; event dated to the January 2025 opening.
The full record
- Status note
- First building opened January 2025; Irving City Council approved a second building in January 2026, with groundbreaking expected in Q2 2026.
- Power note
- First building reported at 24 MW (DCD); the second building was approved with 24 MW of critical capacity (REjournals). Figure shown is the operating first building.
- Evidence
- Primary public records
- Size class
- Under 50 MW (outside main scope; kept for completeness)