Fluidstack Cameron County AI data center campus
Fluidstack started building the first $4 billion phase of an AI data center campus on more than 1,100 acres east of Valley International Airport near Rio Hondo, using closed-loop cooling and no local tax abatement. Also known as: Fluidstack Rio Hondo.
Who is behind it
The record, newest first
Construction Review Online reported AEP Texas will provide transmission, with Fluidstack paying for its own electrical infrastructure; East Rio Hondo WSC will supply water; phase one is targeted for mid-2028 and no anchor tenant has been named. (Construction Review Online, Sept. 11, 2026)
KRGV reported Fluidstack had begun construction on the first phase of a $4 billion campus on 1,100-plus acres after getting a county worksite permit; the company said it would pay full property taxes and cover its own infrastructure costs. (KRGV, Sept. 10, 2026)
Conflicts and open questions
- Separate from the Eneus Energy RGV campus, also proposed east of Valley International Airport.
- Harlingen Mayor Norma Sepulveda said the city lacked authority to stop the project; U.S. Rep. Vicente Gonzalez has said he opposes data center development until the region has enough water, a reliable grid and a long-term plan (KRGV).
The full record
- Status note
- Work on the first phase began after Cameron County issued a worksite permit; phase one targeted for mid-2028.
- Power note
- Fluidstack has not disclosed capacity; a trade outlet's 400-500 MW figure is its own estimate and is not used.
- Evidence
- News reports; primary records not yet obtained
- Size class
- 50 MW or more (tracker scope)