Data center campus · Between Robstown and Calallen, just outside Robstown city limits, Nueces County, Texas

Hut 8 Beacon Point AI data center campus

Under construction as of Oct. 16, 2026

A 525-acre Hut 8 AI campus near Robstown with a 1,000 MW grid connection from AEP Texas and two 15-year leases for 704 MW of IT capacity, now under construction. Also known as: Beacon Point.

Cite← Texas data centers
Anderson CountyAndrews CountyAngelina CountyAransas CountyArcher CountyArmstrong CountyAtascosa CountyAustin CountyBailey CountyBandera CountyBastrop CountyBaylor CountyBee CountyBell CountyBexar CountyBlanco CountyBorden CountyBosque CountyBowie CountyBrazoria CountyBrazos CountyBrewster CountyBriscoe CountyBrooks CountyBrown CountyBurleson CountyBurnet CountyCaldwell CountyCalhoun CountyCallahan CountyCameron CountyCamp CountyCarson CountyCass CountyCastro CountyChambers CountyCherokee CountyChildress CountyClay CountyCochran CountyCoke CountyColeman CountyCollin CountyCollingsworth CountyColorado CountyComal CountyComanche CountyConcho CountyCooke CountyCoryell CountyCottle CountyCrane CountyCrockett CountyCrosby CountyCulberson CountyDallam CountyDallas CountyDawson CountyDeaf Smith CountyDelta CountyDenton CountyDeWitt CountyDickens CountyDimmit CountyDonley CountyDuval CountyEastland CountyEctor CountyEdwards CountyEl Paso CountyEllis CountyErath CountyFalls CountyFannin CountyFayette CountyFisher CountyFloyd CountyFoard CountyFort Bend CountyFranklin CountyFreestone CountyFrio CountyGaines CountyGalveston CountyGarza CountyGillespie CountyGlasscock CountyGoliad CountyGonzales CountyGray CountyGrayson CountyGregg CountyGrimes CountyGuadalupe CountyHale CountyHall CountyHamilton CountyHansford CountyHardeman CountyHardin CountyHarris CountyHarrison CountyHartley CountyHaskell CountyHays CountyHemphill CountyHenderson CountyHidalgo CountyHill CountyHockley CountyHood CountyHopkins CountyHouston CountyHoward CountyHudspeth CountyHunt CountyHutchinson CountyIrion CountyJack CountyJackson CountyJasper CountyJeff Davis CountyJefferson CountyJim Hogg CountyJim Wells CountyJohnson CountyJones CountyKarnes CountyKaufman CountyKendall CountyKenedy CountyKent CountyKerr CountyKimble CountyKing CountyKinney CountyKleberg CountyKnox CountyLa Salle CountyLamar CountyLamb CountyLampasas CountyLavaca CountyLee CountyLeon CountyLiberty CountyLimestone CountyLipscomb CountyLive Oak CountyLlano CountyLoving CountyLubbock CountyLynn CountyMadison CountyMarion CountyMartin CountyMason CountyMatagorda CountyMaverick CountyMcCulloch CountyMcLennan CountyMcMullen CountyMedina CountyMenard CountyMidland CountyMilam CountyMills CountyMitchell CountyMontague CountyMontgomery CountyMoore CountyMorris CountyMotley CountyNacogdoches CountyNavarro CountyNewton CountyNolan CountyNueces CountyOchiltree CountyOldham CountyOrange CountyPalo Pinto CountyPanola CountyParker CountyParmer CountyPecos CountyPolk CountyPotter CountyPresidio CountyRains CountyRandall CountyReagan CountyReal CountyRed River CountyReeves CountyRefugio CountyRoberts CountyRobertson CountyRockwall CountyRunnels CountyRusk CountySabine CountySan Augustine CountySan Jacinto CountySan Patricio CountySan Saba CountySchleicher CountyScurry CountyShackelford CountyShelby CountySherman CountySmith CountySomervell CountyStarr CountyStephens CountySterling CountyStonewall CountySutton CountySwisher CountyTarrant CountyTaylor CountyTerrell CountyTerry CountyThrockmorton CountyTitus CountyTom Green CountyTravis CountyTrinity CountyTyler CountyUpshur CountyUpton CountyUvalde CountyVal Verde CountyVan Zandt CountyVictoria CountyWalker CountyWaller CountyWard CountyWashington CountyWebb CountyWharton CountyWheeler CountyWichita CountyWilbarger CountyWillacy CountyWilliamson CountyWilson CountyWinkler CountyWise CountyWood CountyYoakum CountyYoung CountyZapata CountyZavala CountyHut 8 Beacon Point AI data center campus · Under construction · 1,000 MW
Power1,000MW reported · stated
Site525acres
IT load704MW

Who is behind it

ProjectHut 8 Beacon Point AI data center campusAlso: Beacon Point
Developer and teamHut 8
End userAn unnamed investment-grade company (both phases)

The record, newest first

  1. Construction was reported under way on a first building valued at about $399 million, with completion estimated for November 2027. (BIC Magazine, Oct. 16, 2026)

  2. Because its AEP Texas interconnection was already secured, the campus fell outside the review of new large loads that the governor ordered on Aug. 3. (Corpus Christi Caller-Times (via The Lufkin Daily News), Aug. 11, 2026)

  3. Hut 8 reported a second 352 MW, 15-year lease with the same tenant, bringing contracted IT capacity to 704 MW and base-term contract value to $19.6 billion; it said construction had begun and first energization remained planned for the first quarter of 2027. (Hut 8 Corp. (SEC Form 8-K), July 20, 2026)

  4. Local reporting said the site, just outside Robstown, needed no city or county approval, that Hut 8 had secured about $4.25 billion in bond financing, and that the county judge said the county's outdated abatement policy ruled out a tax break. (KRIS 6 News, June 8, 2026)

  5. Hut 8 signed a 15-year, $9.8 billion lease with an undisclosed tenant for the first 352 MW phase of the 525-acre campus. (KRIS 6 News, May 7, 2026)

Conflicts and open questions

  • A local environmental group raised concerns about the site's proximity to a power station and a water treatment plant, and about noise and light.
  • The 704 MW figure is IT capacity under the two leases; the 1,000 MW figure is grid capacity.

The full record

Power note
1,000 MW is the utility capacity under Hut 8's interconnection agreement with AEP Texas.
Evidence
Primary public records
Size class
50 MW or more (tracker scope)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.