Data center campus · near McCamey, beside the King Mountain wind farm, Upton County, Texas

Hut 8 King Mountain data center

Operating as of Dec. 17, 2025

A 280 MW bitcoin mining data center near McCamey that Hut 8 runs through a 50-50 joint venture, sited next to a West Texas wind farm. Also known as: King Mountain Joint Venture, Echo site (USBTC).

Cite← Texas data centers
Anderson CountyAndrews CountyAngelina CountyAransas CountyArcher CountyArmstrong CountyAtascosa CountyAustin CountyBailey CountyBandera CountyBastrop CountyBaylor CountyBee CountyBell CountyBexar CountyBlanco CountyBorden CountyBosque CountyBowie CountyBrazoria CountyBrazos CountyBrewster CountyBriscoe CountyBrooks CountyBrown CountyBurleson CountyBurnet CountyCaldwell CountyCalhoun CountyCallahan CountyCameron CountyCamp CountyCarson CountyCass CountyCastro CountyChambers CountyCherokee CountyChildress CountyClay CountyCochran CountyCoke CountyColeman CountyCollin CountyCollingsworth CountyColorado CountyComal CountyComanche CountyConcho CountyCooke CountyCoryell CountyCottle CountyCrane CountyCrockett CountyCrosby CountyCulberson CountyDallam CountyDallas CountyDawson CountyDeaf Smith CountyDelta CountyDenton CountyDeWitt CountyDickens CountyDimmit CountyDonley CountyDuval CountyEastland CountyEctor CountyEdwards CountyEl Paso CountyEllis CountyErath CountyFalls CountyFannin CountyFayette CountyFisher CountyFloyd CountyFoard CountyFort Bend CountyFranklin CountyFreestone CountyFrio CountyGaines CountyGalveston CountyGarza CountyGillespie CountyGlasscock CountyGoliad CountyGonzales CountyGray CountyGrayson CountyGregg CountyGrimes CountyGuadalupe CountyHale CountyHall CountyHamilton CountyHansford CountyHardeman CountyHardin CountyHarris CountyHarrison CountyHartley CountyHaskell CountyHays CountyHemphill CountyHenderson CountyHidalgo CountyHill CountyHockley CountyHood CountyHopkins CountyHouston CountyHoward CountyHudspeth CountyHunt CountyHutchinson CountyIrion CountyJack CountyJackson CountyJasper CountyJeff Davis CountyJefferson CountyJim Hogg CountyJim Wells CountyJohnson CountyJones CountyKarnes CountyKaufman CountyKendall CountyKenedy CountyKent CountyKerr CountyKimble CountyKing CountyKinney CountyKleberg CountyKnox CountyLa Salle CountyLamar CountyLamb CountyLampasas CountyLavaca CountyLee CountyLeon CountyLiberty CountyLimestone CountyLipscomb CountyLive Oak CountyLlano CountyLoving CountyLubbock CountyLynn CountyMadison CountyMarion CountyMartin CountyMason CountyMatagorda CountyMaverick CountyMcCulloch CountyMcLennan CountyMcMullen CountyMedina CountyMenard CountyMidland CountyMilam CountyMills CountyMitchell CountyMontague CountyMontgomery CountyMoore CountyMorris CountyMotley CountyNacogdoches CountyNavarro CountyNewton CountyNolan CountyNueces CountyOchiltree CountyOldham CountyOrange CountyPalo Pinto CountyPanola CountyParker CountyParmer CountyPecos CountyPolk CountyPotter CountyPresidio CountyRains CountyRandall CountyReagan CountyReal CountyRed River CountyReeves CountyRefugio CountyRoberts CountyRobertson CountyRockwall CountyRunnels CountyRusk CountySabine CountySan Augustine CountySan Jacinto CountySan Patricio CountySan Saba CountySchleicher CountyScurry CountyShackelford CountyShelby CountySherman CountySmith CountySomervell CountyStarr CountyStephens CountySterling CountyStonewall CountySutton CountySwisher CountyTarrant CountyTaylor CountyTerrell CountyTerry CountyThrockmorton CountyTitus CountyTom Green CountyTravis CountyTrinity CountyTyler CountyUpshur CountyUpton CountyUvalde CountyVal Verde CountyVan Zandt CountyVictoria CountyWalker CountyWaller CountyWard CountyWashington CountyWebb CountyWharton CountyWheeler CountyWichita CountyWilbarger CountyWillacy CountyWilliamson CountyWilson CountyWinkler CountyWise CountyWood CountyYoakum CountyYoung CountyZapata CountyZavala CountyHut 8 King Mountain data center · Operating · 280 MW
Power280MW reported · record

Who is behind it

ProjectHut 8 King Mountain data centerAlso: King Mountain Joint Venture, Echo site (USBTC)
Developer and teamHut 8 (through King Mountain Joint Venture (50% Hut 8 via USBTC))
NextEra Energy (JV partner)
End userNot found in the recordsNot yet named in any record or credited report we have found.

The record, newest first

  1. Hut 8's platform page lists King Mountain at McCamey, Texas, as an ASIC compute site. (Hut 8, Oct. 31, 2026)

  2. In an SEC filing, Hut 8 grouped King Mountain with its Tier I ASIC compute data centers. (Hut 8 Corp. (SEC EDGAR, Exhibit 99.2), Dec. 17, 2025)

  3. Hut 8 listed King Mountain at 280 MW and counted the whole site in its self-mining operations. (Hut 8, Nov. 4, 2024)

  4. USBTC described its Upton County site as co-located with a wind farm and said it had joined the joint venture with NextEra in December 2022 by buying Compute North's half. (Business Wire, May 17, 2023)

  5. Ahead of its merger with Hut 8, USBTC disclosed that it owned half of the King Mountain Joint Venture, which held 1.7 EH/s of self-mining capacity in Texas. (Hut 8 Mining Corp. (SEC EDGAR, Rule 425), April 27, 2023)

Conflicts and open questions

  • Bitcoin mining data center; no announced conversion to AI/HPC found.
  • Identifying USBTC's Upton County 'Echo' site with King Mountain rests on both being the wind-farm JV site in Upton County; Hut 8's platform page places King Mountain at McCamey.
  • Coordinates approximate, near McCamey.

The full record

Power note
Energy capacity under management as listed by Hut 8.
Evidence
Primary public records
Size class
50 MW or more (tracker scope)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.