Data center campus · CR 404, just south of Samsung Austin Semiconductor, in Taylor's ETJ near Hutto, Williamson County, Texas
Iron Mountain Hutto data center campus (CR 404)
Proposed
as of March 12, 2026
Iron Mountain is proposing a seven-building data center campus with its own substation on about 500 acres south of Samsung's Taylor chip plant, part of land once planned for the Taylor Meadows subdivision; it would be the company's first Texas data center. Also known as: Iron Mountain Data Centers Hutto.
PowerNot statedNot reported in the records found
Site500acres
Who is behind it
ProjectIron Mountain Hutto data center campus (CR 404)Also: Iron Mountain Data Centers Hutto
Developer and teamIron Mountain Data Centers
End userNot found in the recordsNot yet named in any record or credited report we have found.
The record, newest first
Iron Mountain and its engineer presented the campus to the Hutto City Council and asked for wastewater service in return for community benefits; the council took no action. (Taylor Press, March 18, 2026; Community Impact, March 19, 2026)
Conflicts and open questions
- The developer told Hutto it does not plan to annex into any city.
- Construction was described as taking about three years.
The full record
- Status note
- Pitched to Hutto City Council for wastewater service; no council action reported.
- Power note
- Not reported for this campus.
- Evidence
- News reports; primary records not yet obtained
- Size class
- 50 MW or more (tracker scope)